Capital Plan 2015 - 2019  
Bridges and Tunnels  
Toll Plazas & Atms   Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Agency-Wide
Installation of Rotating Prism Signs (RPS) at the Bronx-Whitestone, Throgs Neck and Verrazano-Narrows Bridges   Complete   $1,630,918 $1,630,918 0% Dec 2015 Dec 2015 Dec 2017 Dec 2017
Install and Integrate IP traffic cameras at all B & T facilities   Planning  $10,274,509 $10,274,509 0% 2019 2019 2022 2022
Develop a comprehensive and effective Traffic and Incident Management System by building upon the current Transmit and Video Detection Systems Construction $2,949,843 $2,949,843 0% 2017 2019 2020 2021
Replacement and upgrade of existing Advanced Management System (ATMS) and subsystems at all Nine Facilities and Operations Control and Command Center (OCCC)   Planning  $8,111,891 $8,111,891 0% 2018 2018 2020 2020
Replacement and Upgrade of Existing Toll Systems and Exploration of Future Tolling Technologies and Systems Construction $91,513,914 $91,513,914 0% 2017 2016 2021 2021
Rehabilitation/Upgrades to Toll Plaza Structural Elements Construction $42,650,724 $42,650,724 0% 2017 2017 2022 2022
Bronx Whitestone Bridge
Implement Open Road Tolling (ORT) /Cashless Tolling on Bronx-Whitestone Bridge Construction $47,844,325 $47,844,325 0% Mar 2017 Mar 2017 Oct 2017 Oct 2017
Cross Bay Bridge
Implement Open Road Tolling (ORT) /Cashless Tolling on Cross Bay Bridge Construction $22,715,426 $22,715,426 0% Mar 2017 Mar 2017 Apr 2017 Apr 2017
Hugh L. Carey Tunnel
Implement Open Road Tolling (ORT) /Cashless Tolling on Hugh L Carey Tunnel Construction $26,279,340 $26,279,340 0% Nov 2016 Nov 2016 Jan 2017 Jan 2017
Henry Hudson Bridge
Toll Plaza finishes on the Henry Hudson Bridge Construction $7,660,540 $7,660,540 0%
Construction for the replacement of the decks and supporting structure on the Upper Level, the Lower Level South Approach Deck, and the Concrete Cellular Structure including the maintenance garage - Henry Hudson Bridge Construction $96,473,390 $96,473,390 0% Apr 2017 Apr 2017 May 2021 May 2021
Marine Parkway Bridge
Implement Open Road Tolling (ORT) /Cashless Tolling on Marine Parkway Bridge Construction $22,909,853 $22,909,853 0% Mar 2017 Mar 2017 Apr 2017 Apr 2017
Queens Midtown Tunnel
Implement Open Road Tolling (ORT) /Cashless Tolling on Queens Midtown Tunnel Construction $38,051,496 $38,051,496 0% Nov 2016 Nov 2016 Jan 2017 Jan 2017
Robert F. Kennedy Bridge
Implement Open Road Tolling (ORT) /Cashless Tolling on Robert F. Kennedy Bridge Construction $78,785,603 $78,785,603 0% Oct 2016 Oct 2016 Jun 2017 Jun 2017
Throgs Neck Bridge
Implement Open Road Tolling (ORT) /Cashless Tolling on Throgs Neck Bridge Construction $53,739,022 $53,739,022 0% Mar 2017 Mar 2017 Apr 2017 Apr 2017
Verrazano-Narrows Bridge
Implement Open Road Tolling (ORT) /Cashless Tolling on Verrazano- Narrows Bridge Construction $70,226,353 $70,226,353 0% Mar 2017 Mar 2017 Apr 2017 Apr 2017
Number of Projects for MTA Bridges & Tunnels = 16