Capital Plan 2010 - 2014 
New York City Transit 
Signals & Communications   Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Signal Modernization
Modification of Signal Control Lines - Phase 4   Complete   $24,191,268 $23,738,696 (2%) Aug 2011 Aug 2011 Nov 2013 Feb 2014
Replace Signal Messenger Brackets on the Brighton Line  Superseded $0 $0 0% 2013
Modernize Signal Interlocking at Church Avenue on the Culver Line Construction $184,784,442 $183,262,926 (1%) Jun 2010 Jun 2010 Aug 2014 2021
Replace Solid State Signal Equipment at 13 Locations   Complete   $13,137,772 $13,137,772 0% 2010 May 2011 Nov 2012 Apr 2015
Convert R-142 Railcars for Communications-Based Train Control on the Flushing Line   Complete   $224,777,244 $224,777,244 0% 2010 Dec 2011 Feb 2016 Jun 2016
Support / Removals for Communications-Based Train Control on the Flushing Line Construction $187,098,482 $187,098,482 0% Nov 2010 Nov 2010 Nov 2016 2019
Install Station Time Signal Enhancements on the Lexington Avenue Line - Phase 2   Complete   $27,639,834 $26,598,709 (4%) Sep 2011 Sep 2011 May 2014 May 2014
Replace Stop Cables for Signals - Phase 4   Complete   $2,301,783 $2,301,783 0% Jun 2011 Jun 2011 May 2014 Oct 2013
Modernize Signal Interlockings at 71st Avenue and Union Turnpike on the Queens Boulevard Line   Complete   $297,896,714 $297,896,522 0% Nov 2012 Nov 2012 Apr 2017 Jun 2018
Install Communications-Based Train Control Signals Test Track on the Culver Line - Phase 2   Complete   $84,900,000 $84,407,789 (1%) Sep 2011 Sep 2011 Sep 2015 Dec 2015
Modifications to Signal Control Lines - Phase 5   Complete   $9,237,502 $9,237,502 0% 2012 Dec 2013 May 2015 May 2015
Modernize Signals and Interlockings on the Dyre Avenue Line   Complete   $237,121,531 $237,121,531 0% 2012 Apr 2013 Jul 2017 Dec 2017
Modernize Signal Interlocking at Roosevelt Avenue on the Queens Boulevard Line   Complete   $101,355,148 $98,391,393 (3%) 2012 Jan 2013 Dec 2016 Dec 2016
Modernize Signal Interlocking at 34th Street on the 6th Avenue Line Construction $180,002,100 $180,165,294 0% 2012 Apr 2014 2018 2018
Modernize Signal Interlocking at West 4th Street on the 6th Avenue Line Construction $174,106,895 $174,244,938 0% 2012 Jul 2014 2018 2018
Modification of Signal Key-By Circuits - Phase 3   Complete   $13,562,372 $12,183,219 (10%) 2013 Apr 2014 Jun 2016 Jun 2016
Install Communication-Based Train Control on the Queens Boulevard Line West - Phase 1 Construction $117,308,992 $117,900,978 1% 2013 Aug 2015 2019 2021
Modernize Signal Interlocking at Jay Street on the 6th Avenue Line - Design Only  Superseded $0 $0 0% 2014 2016
Rehabilitation of Ducts and Cables, Steinway Tube   Complete   $50,193,867 $53,877,195 7% Jan 2012 Jan 2012 Jan 2015 Sep 2015
Communications-Based Train Control: Equipment Supplier Interoperability Construction $4,995,209 $4,885,815 (2%) 2014 Sep 2015 2018 2019
Replacement of Automatic Train Supervision A-Division and Communications-Based Train Control Status Boards at the Rail Control Center   Complete   $6,631,911 $6,631,911 0% Feb 2014 Feb 2014 Oct 2015 Oct 2015
Automated Train Supervision: Hardware and Software Upgrade   Complete   $5,900,000 $5,900,000 0% 2015 May 2013 2015 Dec 2016
Modernize Signal Interlockings at 4 Locations on the 6th Avenue Line - Design Only   Complete   $2,787,488 $2,787,488 0% Jun 2014 Jun 2014 Jun 2016 Jun 2015
Modernize Signal Interlocking at Kings Highway on the Culver Line - Design Only   Complete   $0 $184,315 0% Dec 2013 Dec 2013 May 2015 May 2015
AC to DC Line Relay Conversions on the Fulton Line   Complete   $5,405,279 $5,405,279 0% Apr 2014 Apr 2014 Feb 2015 Feb 2015
AC to DC Line Relay Conversion on the Fulton Line  Superseded $0 $0 0% Jan 2015 2017
Modifications to Signal Control Lines - Phase 6  Superseded $0 $0 0% Apr 2015 2019
Signal Fire Room Suppression, Phase 2 - Design Only  Superseded $0 $0 0% Oct 2015 2017
Communications Systems
Replacement of Fiber Optic Cable - Phase 1 Construction $11,987,526 $11,987,526 0% 2012 Mar 2016 2018 2019
Application Cutover to SONET/ATM Fiber Optic Network - Phase 1   Design    $12,998,315 $12,998,315 0% 2012 2018 2021
Police Radio Time Domain Interference and Enhancement   Complete   $5,160,007 $5,160,007 0% 2010 Dec 2015
Public Address/Customer Info Screen Systems Construction $65,987,227 $64,606,648 (2%) Dec 2010 Dec 2010 May 2014 2018
Upgrade/Expansion of Communication Rooms - Phase 1 Construction $17,355,243 $17,638,553 2% 2012 Jan 2016 2017 2018
Replacement of Subway Radio Portable Units Construction $6,719,210 $6,719,210 0% Sep 2010 Sep 2010 Sep 2011 2018
Upgrade/Replacement of Copper Communications Cable - Phase 2   Complete   $9,597,375 $9,953,852 4% 2011 Mar 2012 Sep 2013 Aug 2013
Upgrade/Replacement of VHF Subway Radio System   Complete   $197,646,831 $197,629,846 0% 2010 Feb 2012 Jul 2016 Dec 2016
Upgrade Heating, Ventilation and Air Conditioning (HVAC) Systems in Communication Rooms - Phase 2 (SBMP)   Complete   $794,004 $794,004 0% 2010 Jun 2012 Feb 2013 Feb 2013
Private Branch Exchange (PBX) System Upgrades - Design Only   Complete   $2,412,719 $3,396,053 41% 2012 Mar 2013 2017 Jan 2016
Upgrade/Replacement of Antenna Cable - Design Only   Complete   $2,296,743 $1,518,347 (34%) 2013 Feb 2016 2016 Nov 2017
Upgrade/Replacement of Copper Communications Cable - Phase 3   Complete   $14,999,939 $15,051,537 0% 2013 Oct 2014 Jun 2016 Jun 2016
Upgrade Heating, Ventilation and Air Conditioning (HVAC) Systems in Communication Rooms - Phase 3  Superseded $0 $0 0% 2013
Integrated Service Information & Management B-Division (ISIM-B) Construction $14,963,137 $13,707,807 (8%) 2010 Feb 2012 2019
Replacement of Copper Communications Cable   Complete   $3,315,848 $3,328,408 0% 2010 Jan 2009 Mar 2012 Jun 2012
Waterproofing of Communication Rooms   Complete   $8,648,298 $6,882,960 (20%) 2010 Jul 2013 Jun 2015 Jun 2015
Upgrade Ventilation Systems in 19 Communication Rooms   Complete   $10,873,953 $9,443,568 (13%) 2014 Dec 2015 2015 Jun 2017
Passenger Station Local Area Network at 30 Stations   Complete   $26,514,729 $27,516,874 4% 2013 May 2014 2016 Jun 2017
Help Point at 93 Stations   Complete   $75,989,570 $70,212,072 (8%) Mar 2013 Aug 2015 Dec 2016
Passenger Station Local Area Network at 68 Stations Construction $7,296,050 $6,526,938 (11%) Sep 2016 Jun 2014 2018
Waterproofing of Communication Rooms at 5 Locations (SBMP)   Complete   $660,040 $660,040 0% May 2013 May 2013 May 2014 May 2014
Waterproofing of Communication Rooms at 2 Locations   Complete   $245,000 $245,000 0% Apr 2015 Jun 2015 Jun 2015
Integrated Service Information & Management B-Division, Module 1 Construction $58,865,354 $59,160,238 1% 2016 Apr 2015 May 2015 2018
Track Intrusion Detection System Pilot   Complete   $5,275,692 $3,385,267 (36%) Nov 2013 Nov 2013 Jul 2015 Jul 2015
Integrated Service Information & Management B-Division, Module 1, Group 1  Superseded $0 $0 0% 2014 2015
Integrated Service Information & Management B-Division, Module 1, Group 2  Superseded $0 $0 0% 2015 2016
Integrated Service Information & Management B-Division, Module 1, Group 3  Superseded $0 $0 0% 2015 2016
Integrated Service Information & Management B-Division, Module 2 Construction $69,685,669 $67,724,658 (3%) 2015 Jan 2016 2017 2019
Install Help Point Systems at 61 Stations   Complete   $27,842,545 $23,453,288 (16%) Sep 2014 Sep 2014 2015 Nov 2016
Help Point at 121 Street Station and Cypress Hills Station on the Jamaica Line   Complete   $1,406,341 $1,232,390 (12%) Dec 2014 Dec 2014 Oct 2015 Oct 2015
Help Point at Knickerbocker Ave Station on the Myrtle Ave line and Sutter Ave Station on the Canarsie Line   Complete   $1,372,337 $1,266,058 (8%) Dec 2014 Dec 2014 Oct 2015 Oct 2015
Replacement of Copper Communications Cable, Phase 4 - Design Only   Complete   $0 $209,000 0% Jul 2014 Jul 2014 Dec 2015 Dec 2015
Passenger Station Local Area Network at 3 Stations on the Crosstown Line   Complete   $2,419,164 $303,557 (87%) Jan 2014 Jan 2014 Jun 2014 Jun 2014
Integrated Service Information & Management B-Division, Module 3 Construction $10,221,450 $11,552,554 13% 2016 Jul 2018 2020 2022
Platform Screen Doors Pilot - Design Only   Complete   $0 $1,357,317 0% Oct 2014 Oct 2014 Dec 2016 Dec 2016
Help Point at Junius Street Station on the New Lots Avenue Line and Kingsbridge Road Station on the Jerome Line (SBMP)   Complete   $1,328,635 $1,218,591 (8%) Apr 2015 Apr 2015 Apr 2016 Apr 2016
Help Point at Livonia Avenue and New Lots Avenue Stations on the Canarsie Line (SBMP)   Complete   $1,395,103 $1,301,335 (7%) Apr 2015 Apr 2015 Apr 2016 Apr 2016
Replace UHF T-Band Radio System - Design Only  Superseded $0 $0 0% 2016 2017
Upgrade of SONET/ATM Equipment  Superseded $0 $0 0% 2017
Upgrade of Copper Cable at Livingston Plaza  Superseded $0 $0 0% 2015 2016
Help Point at 64 Stations   Complete   $0 $253,873 0% Feb 2015 Feb 2015 Jun 2016 Jun 2016
Help Point at 16 Stations  Superseded $0 $0 0% Feb 2015 2016
Help Point at 90th, 103rd, and 111th Street Stations on the Flushing Line (SBMP)   Complete   $1,655,039 $1,320,204 (20%) Jul 2015 Jul 2015 Feb 2016 Feb 2016
Upgrade of Asynchronous Fiber Optic Network to SONET - Design Only   Complete   $2,251,994 $2,184,513 (3%) Apr 2015 Apr 2015 Aug 2016 Aug 2016
Help Point: Purchase of 300 Access Node Units  Superseded $0 $0 0% Mar 2015 May 2015
LiftNet Transition to Ethernet - Design Only  Superseded $0 $0 0% 2016 2018
Help Point at 13 Stations   Complete   $0 $244,000 0% Oct 2015 Oct 2015 Nov 2016 Jan 2016
Replace Server Hardware at the Rail Control Center and the Backup Control Center Construction $2,100,000 $2,100,000 0% Feb 2016 Feb 2016 2016 2019
Antenna Cable Replacement for 2nd Avenue-63rd Street Connection  Superseded $0 $0 0% Jan 2016 Jun 2016
Police Radio System: Enhanced Coverage   Complete   $0 $2,856,349 0% 2017 May 2016 Dec 2016
B-Division Beacon Train Arrival System Construction $20,000,000 $24,987,862 25% Dec 2016 2018
Integrated Service Information & Management B-Division, Module 5A   Design    $20,000,000 $20,000,000 0% 2018
Upgrade Access Nodes at 60 Stations Construction $0 $2,868,984 0% Sep 2018 Sep 2018 2019 2019
Number of Projects for New York City Transit = 81