Capital Plan 2010 - 2014  
Metropolitan Transportation Authority   Projects with Increases or Decreases Between (9.99%) and 9.99%  
      Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Staten Island Railway
Structural Repairs at Eight Staten Island Railway Stations Complete $14,430,432 $14,168,642 (2%) 2010 Sep 2011 Sep 2013 Dec 2015
Rehabilitation of 8 Bridges and 1 Culvert on the Staten Island Railway Complete $18,301,602 $17,464,588 (5%) Jun 2011 Jun 2011 Jun 2013 Jun 2014
Rehabilitation of St. George Interlocking Complete $14,212,175 $14,094,552 (1%) 2012 Sep 2014 2016 Mar 2017
Construction of New Power Substation: Prince's Bay Complete $25,193,331 $22,901,165 (9%) 2012 Oct 2014 Dec 2017 Dec 2017
Construction of New Station: Arthur Kill Complete $23,465,687 $24,880,380 6% 2012 Jul 2013 2015 Jun 2017
Construction of New Power Substation: Tottenville - Design Only Complete $0 $170,000 0% Feb 2015 Feb 2015 Jul 2015 Jul 2015
Construction of New Power Substation: New Dorp - Design Only Complete $0 $263,431 0% Feb 2015 Feb 2015 Jul 2015 Oct 2016
Construction of New Power Substation: Clifton - Design Only Complete $0 $169,000 0% Feb 2015 Feb 2015 Jul 2015 Oct 2016
Number of Projects for SIRTOA = 8