Projects in Original Plan
Capital Plan 2010 - 2014 
SIRTOA  Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Staten Island Railway
Structural Repairs at Eight Staten Island Railway Stations Complete $14,430,432 $14,168,642 (2%) 2010 Sep 2011 Sep 2013 Dec 2015
Rehabilitation of 8 Bridges and 1 Culvert on the Staten Island Railway Complete $18,301,602 $17,464,588 (5%) Jun 2011 Jun 2011 Jun 2013 Jun 2014
Rehabilitation of St. George Interlocking Complete $14,212,175 $13,997,204 (2%) 2012 Sep 2014 2016 Mar 2017
Retrofit Railcars for Staten Island Railway Service Superseded $0 $0 0% 2012 2016
Construction of New Power Substation: Prince's Bay Complete $25,193,331 $24,193,331 (4%) 2012 Oct 2014 Dec 2017 Dec 2017
Rehabilitation of 5 Circuit Breaker Houses Superseded $0 $0 0% 2013
Installation of Composite Contact Rail Superseded $0 $0 0% 2013
Construction of New Station: Arthur Kill Complete $23,465,687 $25,265,687 8% 2012 Jul 2013 2015 Jun 2017
Staten Island Railway: UHF T-Band Radio System Replacement - Design Only Superseded $0 $0 0% Oct 2016 2017
Number of Projects for SIRTOA = 9