Projects with No Budget Changes
Capital Plan 2010 - 2014 
MTA Interagency  Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
MTA BSC / Facilities Rehab
Complete implementation of MTA Business Service Center Complete $75,000,000 $75,000,000 0% 2010 Mar 2009 Mar 2012 Mar 2012
Rehabilitation of Jay Street Building Complete $60,000,000 $60,000,000 0% 2010 Jun 2012 Sep 2014 Mar 2015
MTA Planning
Tappan Zee Bridge Rail Study (MTA Share) Complete $900,000 $900,000 0% 2010 2011 Dec 2014 Dec 2015
Penn Station Access Study Complete $2,000,000 $2,000,000 0% Oct 2012 Oct 2012 Dec 2013 2016
Number of Projects for MTA Interagency = 4