Capital Plan 2010 - 2014 
MTA Interagency  Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Mta Mentoring Program Admin
MTA Mentoring Program Administration   Complete   $28,484,885 $28,575,885 0% Sep 2010 Sep 2010 Dec 2014 Dec 2016
MTA BSC / Facilities Rehab
Complete implementation of MTA Business Service Center   Complete   $75,000,000 $75,000,000 0% 2010 Mar 2009 Mar 2012 Mar 2012
Rehabilitation of Jay Street Building   Complete   $60,000,000 $60,000,000 0% 2010 Jun 2012 Sep 2014 Mar 2015
MTA Planning
Tappan Zee Bridge Rail Study (MTA Share)   Complete   $900,000 $900,000 0% 2010 2011 Dec 2014 Dec 2015
Penn Station Access Study   Complete   $2,000,000 $2,000,000 0% Oct 2012 Oct 2012 Dec 2013 2016
Number of Projects for MTA Interagency = 5