Capital Plan 2010 - 2014  
Metro-North Railroad   Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Rolling Stock
Purchase Diesel Locomotives for Shuttle/Switching Service  Superseded $0 $0 0% 2012 2014
Stations
Grand Central Terminal Trainshed Track Structure Pilot Replacement Program  Superseded $0 $0 0% 2012 2014
Grand Central Terminal Platform Edge Rehabilitation  Superseded $0 $0 0% 2012 2013
Grand Central Terminal Customer Communications Improvements  Superseded $0 $0 0% 2012 2014
Harlem-125th St Improvements DES  Superseded $0 $0 0% Oct 2016
Parking Facility Renewals  Superseded $0 $0 0% 2012 2014
Track And Structures
Specialized Structures Equipment  Superseded $0 $0 0% 2010 Dec 2012
Communications And Signals
Centralized Traffic Control and Supervisory Control and Data Acquisition Systems Testing  Superseded $35,000 $4,467 (87%) 2010 Jan 2013
Communication and Signals Maintenance Management System  Superseded $0 $0 0% 2010 Dec 2012
Mobile and Portable Radio Replacement  Superseded $0 $0 0% 2012 Apr 2012
Power
Park Avenue Tunnel and Viaduct Alarm Improvements  Superseded $0 $0 0% 2013
Shops And Yards
Wassaic Yard Expansion  Superseded $0 $0 0% 2012 2014
Port Jervis Yard Expansion  Superseded $0 $0 0% 2012 2014
Number of Projects for Metro-North Railroad = 13