Capital Plan 2010 - 2014  
Long Island Rail Road   Projects Added  
      Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Rolling Stock
Work Locomotives Planning $40,000,000 $40,000,000 0% Nov 2017 Aug 2021
Stations
Escalator Replacement Program Complete $11,674,245 $11,124,010 (5%) Nov 2013 Aug 2014 Jul 2015 Apr 2017
ESA-GCT Unified Trash Collection Complete $0 $0 0% Oct 2015 Oct 2016
Track
East River Tunnel Track Replacement Construction $43,200,000 $43,200,000 0% Mar 2012 Mar 2012 Jan 2018 Oct 2016
2015 Track Program Complete $0 $8,978,639 0% Mar 2015 Mar 2015 Dec 2015 Dec 2015
Line Structures
150th Street - Jamaica Bridge Rehabilitation Construction $21,860,000 $17,245,000 (21%) Jan 2014 Mar 2013 Jan 2016 Jan 2017
Post Avenue Bridge Replacement Design Complete $1,450,000 $879,117 (39%) Mar 2015 Mar 2015 2015 Dec 2016
Shops And Yards
Rolling Stock Support Equipment Complete $0 $0 0% Jul 2015 Dec 2016 Aug 2015
Power
Replacement of Port Washington Substation Construction $26,159,452 $26,159,452 0% Apr 2013 Oct 2016 Mar 2017 May 2018
Replacement of Richmond Hill Substation Construction $16,617,791 $16,617,791 0% Oct 2015 Oct 2015 2019 Dec 2018
Replacement of Penn Station Substation Design $38,200,000 $38,200,000 0% Jan 2018 Feb 2020
Miscellaneous
Speonk Yard Metal Treatment System Construction $2,000,000 $2,000,000 0% Apr 2017 Apr 2017 Dec 2017 Dec 2017
OCIP Design $10,932,832 $10,932,832 0% Dec 2012 Dec 2014 Dec 2017
Sandy Mitigation Grant Support Complete $156,175 $156,175 0% Feb 2014 Feb 2014 Mar 2014 Mar 2014
2015 Program Administration Design $0 $0 0% Feb 2015 Feb 2015 2019
Number of Projects for Long Island Rail Road = 15