Projects with No Budget Changes
Capital Plan 2010 - 2014 
Long Island Rail Road  Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Rolling Stock
Work Locomotives Planning $40,000,000 $40,000,000 0% Nov 2017 Aug 2021
Track
Jamaica Capacity Improvements - Phase One Construction $301,653,240 $301,653,240 0% 2011 May 2014 Jan 2014 Oct 2019
Massapequa Pocket Track Construction $19,600,000 $19,600,000 0% Apr 2012 Apr 2012 Jun 2016 Apr 2019
Second Track Farmingdale to Ronkonkoma - Phase 1 Construction $137,200,000 $137,200,000 0% Dec 2013 Dec 2013 May 2014 Jan 2018
Line Structures
Bridge Rehabilitation Program Complete $24,600,000 $24,600,000 0% Apr 2012 Apr 2012 Jun 2016 Nov 2016
Shops And Yards
Hillside Facility Roof Renewals Construction $6,000,000 $6,000,000 0% Oct 2013 Oct 2013 Jan 2013 Jan 2016
Diesel Locomotive Facility Investments Planning $1,000,000 $1,000,000 0% 2012 Jan 2016
Power
3rd Rail Feeder Cable Upgrade Complete $2,483,397 $2,483,397 0% Mar 2010 Oct 2010 May 2014 Sep 2012
Miscellaneous
Yaphank Landfill Remediation Design $9,100,000 $9,100,000 0% 2011 Feb 2019 Sep 2017 May 2020
Smithtown Viaduct Remediation Design $3,200,000 $3,200,000 0% 2013 Jun 2018 Dec 2014 Jun 2019
Speonk Yard Metal Treatment System Construction $2,000,000 $2,000,000 0% Apr 2017 Apr 2017 Dec 2017 Dec 2017
Number of Projects for Long Island Rail Road = 11