Capital Plan 2010 - 2014 
Capital Construction 
ESA RS / Liability Reserve   Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
ESA RS / Liability Reserve
Rolling Stock Reserve to Support ESA: Reserve for Rolling Stock   Design    $463,000,000 $463,000,000 0% 2012 Dec 2018 Dec 2016 Dec 2022
Liability Reserve   Design    $172,803,113 $103,827,372 (40%) Jan 2010 Jan 2010 2016 2019
Number of Projects for MTA Capital Construction Company = 2