Capital Plan  
Super Storm Sandy  
Depots   Budget
* Recovery/Mitigation projects subject to future
federal appropriation and guidance.
  Schedule
* Schedules for some Recovery/Mitigation projects
are still under development.
 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
New York City Transit -Depots Mitigation: Sandy
Mitigation Reserve: Depots in Flood Zones, Phase 1  Superseded $0 $0 0% * * * *
Mitigation Reserve: Depots in Flood Zones, Phase 2  Superseded $0 $0 0% * * * *
Mitigation Reserve: Bus Rapid Transit - Bus Service Enhancements, Phase 1  Superseded $0 $0 0% * * * *
Mitigation Reserve: Bus Rapid Transit - Bus Service Enhancements, Phase 2  Superseded $0 $0 0% * * * *
Mitigation Reserve: Bus Rapid Transit - Staten Island North Shore: Right of Way  Superseded $0 $0 0% * * * *
Mitigation Reserve: Contingency Planning for Bus Transit Service  Superseded $0 $0 0% * * * *
Mitigation: Various Bus Depots   Design    $59,693,333 $54,102,475 (9%) 2014 2018 2015 2020
Mitigation: Roof Protection at Michael J Quill Depot (SBFP) Construction $0 $3,285,880 0% 2017 Jan 2018 2018 2018
Mitigation: Yukon Bus Depot (SBFP) Construction $0 $2,253,417 0% Apr 2018 Apr 2018 2019 2019
Number of Projects for Super Storm Sandy = 9