* Recovery/Mitigation projects subject to future   federal appropriation and guidance.
* Schedules for some Recovery/Mitigation projects   are still under development.
Capital Plan 
Super Storm Sandy 
Signals & Communications   Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
New York City Transit -Signal/Comm Repairs: Sandy
Recovery: South Ferry Interlocking   Complete   $66,473,393 $58,573,393 (12%) Nov 2014 Nov 2014 2015 Jun 2017
Recovery: Signal Restoration on the Rockaway Line   Complete   $24,987,359 $24,987,001 0% Nov 2012 Nov 2012 Dec 2013 Dec 2013
Recovery: Signals in Under River Tubes - Design Only   Complete   $944,705 $904,544 (4%) Apr 2013 Apr 2013 Mar 2015 Mar 2015
Recovery: 207 Street and 200 Street Interlockings on the 8th Avenue Line   Design    $43,238,549 $43,238,549 0% 2016 2018
Recovery: Signals (Greenpoint Tube)   Complete   $7,002,426 $6,819,344 (3%) Jul 2013 Jul 2013 Oct 2014 Oct 2014
Recovery: Whitehall Street Interlocking on the Broadway Line   Complete   $16,501 $16,501 0% * * * *
Recovery: Signals (Canarsie Tube) Construction $35,567,257 $36,380,305 2% 2016 Apr 2017 2022 2020
Recovery: Signals (Clark Tube) Construction $9,204,970 $9,204,970 0% Sep 2016 Sep 2016 2019 2019
Recovery: Signals (Rutgers Tube)   Planning  $9,964,848 $9,964,848 0% 2021 2021 2024 2024
Recovery: Signals (Cranberry Tube)   Complete   $18,038,416 $18,038,416 0% Dec 2014 Dec 2014 Aug 2017 Aug 2017
Recovery: Signals (53 Street Tube)   Complete   $10,394,141 $10,394,141 0% Apr 2015 Apr 2015 Nov 2017 Nov 2017
Recovery: Signals (Montague Tube)   Complete   $32,848,481 $32,848,481 0% Oct 2013 Oct 2013 Nov 2014 Nov 2014
Recovery: Signal Circuit Modifications (Montague Tube)   Complete   $1,218,183 $1,118,445 (8%) Jun 2013 Jun 2013 Aug 2013 Aug 2013
Recovery: Install Programmable Logic Controller Signal Equipment on the Rockaway Line   Complete   $5,506,093 $5,504,399 0% Dec 2013 Dec 2013 2014 Feb 2015
Recovery: Revenue Facility Microwave Communications System   Complete   $542,066 $513,316 (5%) 2015 May 2014 2016 May 2015
Recovery: Rockaway Park Interlocking   Complete   $2,034 $2,034 0% 2017
Recovery Reserve: South Ferry Signals and Communications Restoration  Superseded $0 $0 0% * * * *
Recovery Reserve: Rockaway Line Signals and Communications Restoration  Superseded $0 $0 0% * * * *
Recovery Reserve: Signals and Communications Restoration at Various Locations  Superseded $0 $0 0% * * * *
Recovery Reserve: Signals Restoration  Superseded $0 $0 0% * * * *
Recovery: Risk Reserve (South Ferry)   Planning  $22,900,000 $22,900,000 0% * * * *
New York City Transit -Signal/Comm Mitigation: Sandy
Mitigation Reserve: System Improvements - Subway Service Flexibility, Phase 1  Superseded $0 $0 0% * * * *
Mitigation Reserve: System Improvements - Subway Service Flexibility, Phase 2  Superseded $0 $0 0% * * * *
Number of Projects for Super Storm Sandy = 23