Capital Plan  
Super Storm Sandy  
Line Equipment   Budget
* Recovery/Mitigation projects subject to future
federal appropriation and guidance.
  Schedule
* Schedules for some Recovery/Mitigation projects
are still under development.
 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
New York City Transit -Line Equipment Repairs: Sandy
Recovery Reserve: South Ferry Line Equipment Restoration  Superseded $0 $0 0% * * * *
Recovery: Line Equipment Restoration at Various Locations - Design Only   Complete   $15,359,496 $13,405,561 (13%) Feb 2013 Feb 2013 2015 Apr 2016
Recovery: Tunnel Lighting (Montague Tube)   Complete   $17,564,561 $17,415,857 (1%) Jul 2013 Jul 2013 Mar 2015 Mar 2015
Recovery: 2 Pump Rooms (Montague Tube)   Complete   $8,289,530 $8,226,633 (1%) Jul 2013 Jul 2013 Mar 2015 Mar 2015
Recovery: Fan Plant (Montague Tube)   Complete   $3,947,596 $3,943,962 0% Jul 2013 Jul 2013 Mar 2015 Mar 2015
Recovery: Tunnel Lighting (Greenpoint Tube)   Complete   $37,049,179 $36,817,159 (1%) Jul 2013 Jul 2013 Dec 2015 Dec 2014
Recovery: Pump Room (Greenpoint Tube)   Complete   $4,714,465 $3,319,164 (30%) Oct 2013 Oct 2013 Aug 2015 Aug 2015
Recovery: Fan Plant (Greenpoint Tube)   Complete   $10,490,021 $10,124,414 (3%) Oct 2013 Oct 2013 Aug 2015 Aug 2015
Recovery: Tunnel Lighting (Canarsie Tube) Construction $53,973,584 $49,331,538 (9%) Apr 2017 Apr 2017 2020 2020
Recovery: Tunnel Lighting (Rutgers Tube)   Planning  $4,392,965 $4,392,965 0% 2021 2021 2024 2024
Recovery: Tunnel Lighting (Joralemon Tube)   Complete   $44,477,300 $44,477,300 0% Jul 2015 Jul 2015 Dec 2017 Dec 2017
Recovery: Pump Room (South Ferry)   Complete   $5,403,075 $3,703,075 (31%) Nov 2014 Nov 2014 Jun 2017 Jun 2017
Recovery: 2 Pump Rooms (Southern Manhattan)   Complete   $7,215,402 $5,123,013 (29%) Jul 2014 Jul 2014 Jan 2017 Jan 2017
Recovery: Pump Room (Canarsie Tube) Construction $19,897,279 $18,011,167 (9%) 2016 Apr 2017 2020 2020
Recovery: Pump Room (207 Street-Broadway / 8th Avenue)   Complete   $4,084,472 $7,448,618 82% Dec 2014 Dec 2014 2016 Sep 2017
Recovery: Pump Room (Steinway Tube)   Complete   $20,983,500 $20,702,820 (1%) Oct 2013 Oct 2013 Nov 2015 Nov 2015
Recovery: Fan Plant (South Ferry)   Complete   $7,307,176 $6,057,176 (17%) Nov 2014 Nov 2014 Jun 2017 Jun 2017
Recovery: 3 Fan Plants (Southern Manhattan)   Complete   $25,711,415 $18,610,997 (28%) Jul 2014 Jul 2014 Jan 2017 Jan 2017
Recovery: 3 Fan Plants (Cranberry and Rutgers Tubes) - Design Only   Complete   $51,848 $51,848 0% Apr 2013 Apr 2013 Jan 2014 Jan 2014
Recovery: Fan Plant (Clark Tube) Construction $5,234,519 $5,234,519 0% 2014 Sep 2016 2019 2019
Recovery: Tunnel Lighting (South Ferry)   Complete   $9,198,732 $9,198,732 0% Nov 2014 Nov 2014 Jun 2017 Jun 2017
Recovery: Tunnel Lighting (200th to 207th Street / 8th Avenue)   Complete   $18,861,646 $19,237,003 2% Dec 2014 Dec 2014 2016 Sep 2017
Recovery Reserve: Line Equipment Restoration at Various Locations  Superseded $0 $0 0% * * * *
Recovery: 2 Pump Rooms (Cranberry Tube)   Complete   $12,501,874 $12,501,874 0% Dec 2014 Dec 2014 Aug 2017 Aug 2017
Recovery: 2 Fan Plants (Cranberry Tube)   Complete   $16,616,778 $16,351,278 (2%) Dec 2014 Dec 2014 Aug 2017 Aug 2017
Recovery: 2 Pump Rooms (Rutgers Tube)   Planning  $6,682,531 $6,682,531 0% 2021 2021 2024 2024
Recovery: Fan Plant (Rutgers Tube)   Planning  $4,392,965 $4,392,965 0% 2021 2021 2024 2024
Recovery: Pump Room (Clark Tube) Construction $7,988,704 $7,988,704 0% Sep 2016 Sep 2016 2019 2019
New York City Transit -Line Equipmt Mitigation: Sandy
Mitigation Reserve: Pumping System Improvements  Superseded $0 $0 0% * * * *
Mitigation Reserve: Subway Equipment Hardening in Flood-Prone Areas, Phase 1  Superseded $0 $0 0% * * * *
Mitigation Reserve: Subway Equipment Hardening in Flood-Prone Areas, Phase 2  Superseded $0 $0 0% * * * *
Mitigation: Conversion of 2 Pump Trains   Complete   $13,885,942 $13,885,942 0% Jan 2013 Jan 2013 2014 Mar 2015
Mitigation: 17 Fan Plants and Adjacent Tunnels Construction $46,480,685 $46,435,094 0% Aug 2013 May 2016 2015 2020
Mitigation: Above-Grade Surface Protection at 6 Fan Plants Construction $6,890,122 $6,890,122 0% Apr 2016 Apr 2016 2018 2018
Mitigation: Deployable Vent Covers (SBFP)   Complete   $3,561,242 $3,561,242 0% Dec 2014 Dec 2014 Jan 2016 Jan 2016
Mitigation: Hatch Replacement and Installation of Mechanical Closure Devices at Various Fan Plants (SBFP)   Complete   $5,190,742 $5,179,667 0% Jan 2015 Jan 2015 Aug 2016 Aug 2016
Mitigation: Hatch Replacement at Various Fan Plants (SBFP)   Complete   $4,709,333 $4,709,333 0% Jan 2015 Jan 2015 2015 Aug 2016
Mitigation: Seal Conduit and Duct Penetrations (SBFP)   Complete   $2,944,910 $2,944,910 0% Feb 2015 Feb 2015 Dec 2015 Dec 2015
Mitigation: Pumping System Improvements for Under River Tubes   Complete   $4,008,004 $4,790,619 20% Dec 2014 Apr 2017
Mitigation: Purchase of Backup Generators Construction $3,512,435 $3,078,150 (12%) Dec 2015 Dec 2015 Aug 2016 2019
Mitigation: 2 Pump Rooms (Joralemon Tube)   Complete   $8,305,187 $8,305,187 0% Jul 2015 Jul 2015 Dec 2017 Dec 2017
Mitigation: Improve Pumping Capacity (Annex Pumps)   Complete   $1,429,816 $1,429,816 0% 2016 2017
Mitigation: Conversion of 2 Pump Trains   Design    $16,570,420 $16,570,420 0% 2017 2018 2020 2021
Mitigation: Pumping System Improvements - Design Only   Complete   $4,585,144 $4,857,572 6% May 2014 May 2014 2016 Jun 2017
Mitigation: Department of Buses Mobile Pumps and Generators Construction $1,660,000 $1,660,000 0% Nov 2017 Nov 2017 2019 2019
Mitigation: 11 Fan Plants Construction $27,435,786 $28,951,421 6% Sep 2016 Sep 2016 2019 2020
Mitigation: 4 Fan Plants Construction $32,963,478 $34,520,893 5% Dec 2016 Dec 2016 2020 2020
Mitigation: Right-of-Way Equipment Hardening   Planning  $26,627,383 $26,351,505 (1%) * * * *
Mitigation: 2 Pump Rooms (Cranberry Tube)   Complete   $3,088,378 $3,088,378 0% Aug 2016 Aug 2016 Aug 2017 Aug 2017
Mitigation: 3 Pump Rooms (Clark Tube) Construction $6,074,200 $6,074,200 0% Sep 2016 Sep 2016 2019 2019
Mitigation: 1 Fan Plant Construction $20,740,823 $5,910,081 (72%) Nov 2017 Nov 2017 2019 2019
Mitigation: 1 Fan Plant (SBFP)  Superseded $231,448 $231,448 0% 2017 2018
Mitigation: Pump Room Enhancements   Planning  $45,000,000 $45,000,000 0% * * * *
Mitigation: Department of Subways Mobile Pumps and Generators   Planning  $192,000 $192,000 0% * * * *
Mitigation: 14 Fan Plants and Adjacent Tunnels - Design Only   Planning  $11,377,415 $11,377,415 0% * * * *
Mitigation: 1 Fan Plant on the Flushing Line   Design    $0 $14,830,742 0% 2019 2019 2020 2020
Mitigation: Steinway Portal Signal Tower   Design    $0 $206,850 0% * * * *
Mitigation: 3 Pump Rooms (53rd St Tube)   Planning  $0 $3,450 0% * * * *
Number of Projects for Super Storm Sandy = 58