Capital Plan  
Super Storm Sandy  
Line Structures   Budget
* Recovery/Mitigation projects subject to future
federal appropriation and guidance.
  Schedule
* Schedules for some Recovery/Mitigation projects
are still under development.
 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Long Island Rail Road -Line Structure Repairs: Sandy
East River Tunnel Restoration of Signal System Reliability   Planning  $121,803,700 $121,803,700 0% Jun 2013 2018
Wreck Lead Bridge Systems Restoration   Complete   $14,859,812 $14,859,812 0% Apr 2013 Apr 2013 Nov 2017 Sep 2017
Long Island Rail Road -Line Structre Mitigation:Sandy
Atlantic Ave Tunnels Mitigation Construction $9,900,000 $9,900,000 0% Oct 2014 Oct 2016 Jun 2018
Number of Projects for Super Storm Sandy = 3