Capital Plan  
Super Storm Sandy  
Miscellaneous   Budget
* Recovery/Mitigation projects subject to future
federal appropriation and guidance.
  Schedule
* Schedules for some Recovery/Mitigation projects
are still under development.
 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
MTA Capital Construction Company -Miscellaneous Repairs: Sandy
East Side Access Impacts   Complete   $25,725 $25,725 0% Oct 2012 Oct 2012 Oct 2012 Oct 2012
Second Avenue Subway Impacts   Complete   $63,973 $63,972 0% Oct 2012 Oct 2012 Oct 2012 Oct 2012
Fulton Center Impacts   Complete   $16,582 $16,582 0% Oct 2012 Oct 2012 Oct 2012 Oct 2012
Number of Projects for Super Storm Sandy = 3