* Recovery/Mitigation projects subject to future   federal appropriation and guidance.
* Schedules for some Recovery/Mitigation projects   are still under development.
Capital Plan 
Super Storm Sandy 
Roadways & Decks   Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
MTA Bridges & Tunnels -Roadway/Deck Repairs: Sandy
Restore Hugh Carey Tunnel roadway after Super Storm Sandy   Complete   $7,492,786 $7,492,786 0% Nov 2014 Dec 2014 Nov 2019 Mar 2018
Restore Queens Midtown Tunnel roadway after Super Storm Sandy   Complete   $1,467,743 $1,467,743 0% Nov 2014 Apr 2015 Nov 2018 May 2018
Number of Projects for Super Storm Sandy = 2