* Schedules for some Recovery/Mitigation projects   are still under development.
Capital Plan 2010 - 2014 
Metropolitan Transportation Authority  Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Super Storm Sandy - Passenger Stations
Recovery: Shaft Excavation - 1 Avenue (Canarsie Tube) Construction $13,867,323 $17,835,502 29% 2016 Apr 2017 2020 2020
Mitigation: Critical Room Resiliency Construction $22,659,179 $22,659,179 0% Mar 2016 Mar 2016 2018 2018
Mitigation: Street Level Openings Construction $45,924,466 $46,699,866 2% Jul 2016 Jul 2016 2019 2020
Mitigation: Internal Station Hardening at 7 Stations Construction $5,031,262 $5,191,552 3% Jul 2016 Jul 2016 2020 2020
Mitigation: Street Level Openings at 7 Stations and 1 Fan Plant Construction $68,218,858 $68,218,858 0% 2016 Apr 2017 2020 2021
Mitigation: Street Level Openings at 9 Stations Construction $60,405,786 $60,405,786 0% 2016 Mar 2017 2019 2020
Mitigation: Internal Station Hardening at 3 Stations Construction $2,123,020 $2,123,020 0% Apr 2017 Apr 2017 2021 2021
Super Storm Sandy - Track
Recovery: Mainline Track (Canarsie Tube) Construction $39,851,445 $34,306,612 (14%) 2016 Apr 2017 2020 2020
Recovery: Mainline Track (Clark Tube) Construction $9,581,139 $9,581,139 0% Sep 2016 Sep 2016 2019 2019
Super Storm Sandy - Line Equipment
Recovery: Tunnel Lighting (Canarsie Tube) Construction $53,973,584 $49,331,538 (9%) Apr 2017 Apr 2017 2020 2020
Recovery: Pump Room (Canarsie Tube) Construction $19,897,279 $18,011,167 (9%) 2016 Apr 2017 2020 2020
Recovery: Fan Plant (Clark Tube) Construction $5,234,519 $5,234,519 0% 2014 Sep 2016 2019 2019
Recovery: Pump Room (Clark Tube) Construction $7,988,704 $7,988,704 0% Sep 2016 Sep 2016 2019 2019
Mitigation: 17 Fan Plants and Adjacent Tunnels Construction $46,480,685 $46,435,094 0% Aug 2013 May 2016 2015 2020
Mitigation: Above-Grade Surface Protection at 6 Fan Plants Construction $6,890,122 $6,890,122 0% Apr 2016 Apr 2016 2018 2018
Mitigation: Purchase of Backup Generators Construction $3,512,435 $3,512,435 0% Dec 2015 Dec 2015 Aug 2016 2018
Mitigation: Department of Buses Mobile Pumps and Generators Construction $1,660,000 $1,660,000 0% Nov 2017 Nov 2017 2019 2019
Mitigation: 11 Fan Plants Construction $27,435,786 $28,951,421 6% Sep 2016 Sep 2016 2019 2020
Mitigation: 4 Fan Plants Construction $32,963,478 $34,520,893 5% Dec 2016 Dec 2016 2020 2020
Mitigation: 3 Pump Rooms (Clark Tube) Construction $6,074,200 $6,074,200 0% Sep 2016 Sep 2016 2019 2019
Mitigation: 1 Fan Plant Construction $20,740,823 $5,910,081 (72%) Nov 2017 Nov 2017 2019 2019
Super Storm Sandy - Line Structures
Mitigation: Long Term Flood Protection at Hammels Wye Construction $2,565,521 $24,885,606 870% Jan 2018 2019
Super Storm Sandy - Signals & Communications
Recovery: Signals (Canarsie Tube) Construction $35,567,257 $35,695,374 0% 2016 Apr 2017 2022 2020
Recovery: Signals (Clark Tube) Construction $9,204,970 $9,204,970 0% Sep 2016 Sep 2016 2019 2019
Super Storm Sandy - Traction Power
Recovery: Power Cable, Communication Cable, Ducts and Rust Coating (Montague Tube) Construction $100,376,685 $99,859,697 (1%) Jul 2013 Jul 2013 Mar 2015 2019
Recovery: 2 Circuit Breaker Houses (Canarsie Tube) Construction $38,209,648 $35,003,468 (8%) 2015 Apr 2017 2022 2020
Recovery: Power Cable, Communication Cable and Ducts (Canarsie Tube) Construction $318,041,665 $318,135,885 0% 2015 Apr 2017 2022 2020
Recovery: Power and Communication Cables (Clark Street Tube) Construction $78,610,429 $78,610,429 0% 2014 Sep 2016 2016 2019
Recovery: Sandy Repair MTA Independent Integrity Monitor Construction $3,000,000 $3,000,000 0% * * * *
Mitigation: Power Cable, Communication Cable and Ducts (Canarsie Tube) Construction $189,649,102 $102,174,607 (46%) 2016 Apr 2017 2020 2020
Super Storm Sandy - Shops & Yards
Recovery: Power Cable at Coney Island Yard Construction $198,298,614 $165,106,969 (17%) 2015 Mar 2018 2019 2022
Mitigation: Near Term Perimeter Protection at Coney Island Yard Construction $13,234,878 $13,234,878 0% Jul 2014 Jul 2014 2014 2019
Mitigation: Long Term Perimeter Protection at Coney Island Yard Construction $516,000,000 $350,540,603 (32%) 2015 Mar 2018 2020 2022
Super Storm Sandy - Depots
Mitigation: Roof Protection at Michael J Quill Depot (SBFP) Construction $0 $3,285,880 0% 2017 Jan 2018 2018 2018
Number of Projects for New York City Transit = 34
 
New York City Transit - Subway Cars
Purchase 300 B-Division Railcars Construction $740,566,286 $740,566,286 0% 2010 Jun 2012 Jan 2017 2019
New York City Transit - Buses
Replace Main Components of (Bus) Integrated Farebox Units Construction $11,019,384 $11,019,384 0% Dec 2010 Dec 2010 Apr 2014 2019
On-Board Audio Visual System - Depot Wi-Fi Construction $3,185,497 $3,599,436 13% 2015 Mar 2016 2016 2019
Purchase 92 Articulated Buses Construction $81,930,464 $84,405,711 3% Mar 2016 Mar 2016 2018 2018
New York City Transit - Passenger Stations
Replacement of MetroCard Electronic Components Construction $16,138,480 $16,340,035 1% 2010 Dec 2011 Jun 2016 2020
New Fare Payment System Construction $127,161,297 $127,161,297 0% 2010 Nov 2017 2023
Rehabilitation of 20 Avenue Station on the Sea Beach Line Construction $30,860,678 $30,267,945 (2%) 2012 Dec 2014 2018 2018
Rehabilitation of 8 Avenue Station on the Sea Beach Line Construction $40,246,801 $40,224,332 0% 2012 Dec 2014 2018 2018
Rehabilitation of Fort Hamilton Parkway Station on the Sea Beach Line Construction $32,154,457 $32,154,457 0% 2012 Dec 2014 2018 2018
Rehabilitation of 18th Avenue Station on the Sea Beach Line Construction $36,510,636 $36,390,636 0% 2012 Dec 2014 2018 2018
Rehabilitation of Kings Highway Station on the Sea Beach Line Construction $33,396,072 $33,496,072 0% 2012 Jan 2015 2018 2018
Rehabilitation of New Utrecht Avenue Station on the Sea Beach Line Construction $29,738,707 $29,746,707 0% 2012 Dec 2014 2018 2018
Rehabilitation of Bay Parkway Station on the Sea Beach Line Construction $41,253,687 $41,253,687 0% 2012 Dec 2014 2018 2018
Rehabilitation of Avenue U Station on the Sea Beach Line Construction $35,258,925 $36,112,010 2% 2012 Jan 2015 2018 2018
Rehabilitation of 86 St Station on the Sea Beach Line Construction $29,189,354 $29,189,354 0% 2012 Jan 2015 2018 2018
Renewal of Avenue X Station on the Culver Line Construction $19,399,156 $21,467,394 11% 2013 Sep 2014 2017 2018
Renewal of Avenue U Station on the Culver Line Construction $16,932,003 $15,766,974 (7%) 2013 Sep 2014 2017 2018
Renewal of Avenue P Station on the Culver Line Construction $15,485,750 $15,124,576 (2%) 2013 Sep 2014 2017 2018
Renewal of Bay Parkway Station on the Culver Line Construction $14,486,645 $15,695,252 8% 2013 Sep 2014 2017 2018
Renewal of 18 Avenue Station on the Culver Line Construction $19,670,620 $25,817,701 31% 2013 Sep 2014 2017 2018
Renewal of Ditmas Avenue Station on the Culver Line Construction $21,156,687 $19,725,690 (7%) 2013 Sep 2014 2017 2018
Renewal of Avenue I Station on the Culver Line Construction $17,226,818 $20,385,559 18% 2013 Sep 2014 2017 2018
Component Repairs at 4 Stations on the Jamaica Line Construction $82,136,095 $82,136,095 0% 2012 Jun 2016 2019
Component Repairs at 2 Stations on the Culver Line Construction $21,309,043 $23,617,903 11% 2013 Sep 2014 2017 2018
Ventilator Repairs at 5 Locations in Upper Manhattan and the Bronx Construction $5,872,617 $5,872,617 0% 2013 Nov 2014 2015 2018
Component Repairs at 3 Stations on the 8th Avenue Line Construction $28,377,329 $29,003,129 2% 2014 Mar 2017 2019
Repair of 5 Street Stairs at Rector Street on the Broadway Line (SBMP) Construction $3,624,412 $3,893,136 7% 2014 Oct 2016 2018 2018
Ventilator Repairs at 8 Locations in Lower Manhattan Construction $7,322,388 $7,322,388 0% 2014 Jan 2015 2016 2018
Station Painting at 3 Stations on the Jamaica Line Construction $2,842,368 $2,842,368 0% 2015 Jun 2016 2019
Ventilator Repairs at 4 Locations in North Brooklyn Construction $4,990,046 $5,098,682 2% Dec 2015 Dec 2015 2016 2018
Ventilator Repairs at 2 Locations in Southwest Brooklyn Construction $2,940,000 $2,940,000 0% May 2016 May 2016 2016 2018
Water Condition Remedy - 2015 Construction $0 $2,432,991 0% Dec 2015 Dec 2015 2017 2018
Improve Horizontal and Vertical Platform Clearance at Various Locations Construction $11,060,537 $11,060,537 0% 2010 Dec 2017 2019
ADA Accessibility at 57 St Station on the Broadway Line - Phase 2 Construction $35,857,557 $35,857,557 0% 2012 Dec 2017 2017 2021
ADA Accessibility at New Utrecht Avenue Station on the Sea Beach Line and 62 St Station on the West End Line Construction $18,981,803 $18,229,167 (4%) Dec 2014 Dec 2014 2018 2018
ADA Accessibility at 8th Avenue Station on the Sea Beach Line Construction $20,764,420 $20,672,497 0% Dec 2014 Dec 2014 2018 2018
Reserve: Church Street Corridor Improvements Construction $40,000,000 $40,000,000 0% 2013
Reconstruct Cortlandt Street Station - Broadway-7th Avenue Line Construction $110,000,000 $114,990,671 5% Apr 2015 2017 2018
New York City Transit - Line Equipment
Replace Tunnel Lighting from Roosevelt Av-36 St on the Queens Blvd Line Construction $52,148,238 $52,148,238 0% 2012 Jun 2013 Jun 2017 2020
New Vent Plant at 46 St on the Queens Blvd Line Construction $82,338,068 $81,338,068 (1%) 2012 Aug 2013 2016 2018
Replace Ventilation Controls at 22 Locations Construction $16,215,738 $16,215,738 0% 2013 Dec 2014 2017 2018
New York City Transit - Line Structures
Demolish Abandoned Structures Construction $15,150,000 $15,150,000 0% Jun 2012 Jun 2012 Dec 2014 2018
Overcoat Painting from Portal-E 180 St on the White Plains Road Line Construction $36,196,783 $35,971,321 (1%) 2012 Jan 2013 Oct 2015 2021
Rehabilitation of Retaining Wall on the Sea Beach Line Construction $49,203,568 $48,449,061 (2%) 2012 Dec 2014 2018 2018
Priority Structure Repairs on the 4th Av Line Construction $30,865,041 $31,263,719 1% 2013 May 2017 2016 2020
Structural Repairs at 9 Avenue Station on the West End Line Construction $22,703,522 $27,437,869 21% Jul 2012 Jul 2012 Jul 2015 2019
New York City Transit - Signals & Communications
Modernize Signal Interlocking at Church Avenue on the Culver Line Construction $184,784,442 $184,784,442 0% Jun 2010 Jun 2010 Aug 2014 2021
Support / Removals for Communications-Based Train Control on the Flushing Line Construction $187,098,482 $187,098,482 0% Nov 2010 Nov 2010 Nov 2016 2019
Modernize Signal Interlockings at 71st Avenue and Union Turnpike on the Queens Boulevard Line Construction $297,896,714 $297,896,714 0% Nov 2012 Nov 2012 Apr 2017 2018
Modernize Signal Interlocking at 34th Street on the 6th Avenue Line Construction $180,002,100 $180,165,294 0% 2012 Apr 2014 2018 2018
Modernize Signal Interlocking at West 4th Street on the 6th Avenue Line Construction $174,106,895 $174,244,938 0% 2012 Jul 2014 2018 2018
Install Communication-Based Train Control on the Queens Boulevard Line West - Phase 1 Construction $117,308,992 $117,900,978 1% 2013 Aug 2015 2019 2021
Communications-Based Train Control: Equipment Supplier Interoperability Construction $4,995,209 $4,885,815 (2%) 2014 Sep 2015 2018 2019
Replacement of Fiber Optic Cable - Phase 1 Construction $11,987,526 $11,987,526 0% 2012 Mar 2016 2018 2019
Public Address/Customer Info Screen Systems Construction $65,987,227 $65,983,000 0% Dec 2010 Dec 2010 May 2014 2018
Upgrade/Expansion of Communication Rooms - Phase 1 Construction $17,355,243 $17,638,553 2% 2012 Jan 2016 2017 2018
Replacement of Subway Radio Portable Units Construction $6,719,210 $6,719,210 0% Sep 2010 Sep 2010 Sep 2011 2018
Integrated Service Information & Management B-Division (ISIM-B) Construction $14,963,137 $13,707,807 (8%) 2010 Feb 2012 2019
Passenger Station Local Area Network at 68 Stations Construction $7,296,050 $7,296,050 0% Sep 2016 Jun 2014 2018
Integrated Service Information & Management B-Division, Module 1 Construction $58,865,354 $59,160,238 1% 2016 Apr 2015 May 2015 2018
Integrated Service Information & Management B-Division, Module 2 Construction $69,685,669 $67,724,658 (3%) 2015 Jan 2016 2017 2019
Replace Server Hardware at the Rail Control Center and the Backup Control Center Construction $2,100,000 $2,100,000 0% Feb 2016 Feb 2016 2016 2018
B-Division Beacon Train Arrival System Construction $20,000,000 $25,000,000 25% Dec 2016 2018
New York City Transit - Traction Power
Rehabilitate Roof/Enclosure of Concourse-East 144 Street Substation on the Jerome Line (SBMP) Construction $1,404,850 $1,404,850 0% Sep 2012 Sep 2012 Sep 2013 2018
Replace Power System Negative Cables on 4th Avenue Line, Phase 2 Construction $5,000,000 $5,000,000 0% 2013 Dec 2016 2018 2018
Rehab Pearl Street Circuit Breaker House on the Clark St Line Construction $7,900,932 $9,633,611 22% 2014 Jun 2017 2018
New York City Transit - Shops And Yards
Upgrade 207 St Overhaul Shop Heating Plant and Boiler Upgrade Construction $15,854,125 $15,854,125 0% Dec 2010 Dec 2010 Feb 2012 2020
Replace Heavy Shop Equipment Construction $8,184,000 $8,184,000 0% 2012 Jul 2015 2016 2018
Upgrade 207 St Overhaul Shop Equipment Construction $2,242,375 $2,242,375 0% Oct 2012 Jun 2014 2015 2018
Purchase of Overhead Crane for Concourse Maintenance Facility Construction $3,025,400 $883,638 (71%) 2015 Apr 2017 2016 2018
Integrated Wheel and Rail Monitoring and Analytics Construction $4,621,869 $4,621,869 0% Feb 2016 Feb 2016 2017 2018
Purchase and Installation of a 2-Ton Overhead Crane at 207th Street Maintenance Facility Construction $3,025,400 $883,638 (71%) 2016 Apr 2017 2016 2018
New York City Transit - Depots
Replacement of Chassis Washes at Michael J. Quill Bus Depot (SBMP) Construction $1,469,555 $1,469,555 0% 2014 Apr 2015 2016 2018
Upgrade Heating, Ventilation, Air Condition Systems and Rehab Office at East New York Depot Construction $4,830,000 $4,830,000 0% May 2015 May 2015 2016 2018
Kingsbridge Depot Roof Replacement of Annex Building (SBMP) Construction $3,070,000 $3,367,150 10% 2015 Jul 2017 2017 2019
Bus Rapid Transit Construction $30,555,251 $30,551,090 0% 2010 Feb 2011 Dec 2012 2021
Replacement of Bus Radio System Construction $195,254,466 $200,586,046 3% Feb 2012 Feb 2012 Dec 2017 2021
New Bus Command Center Building Construction $52,038,207 $52,038,207 0% 2014 Jun 2015 2016 2018
Removal of In-Ground Lifts at 5 Bus Depots Construction $2,345,700 $2,345,700 0% Jun 2014 Jun 2014 2015 2018
Replacement of Oil-Water Separators at 4 Depots Construction $13,967,782 $19,146,634 37% 2015 Dec 2017 2018 2019
New York City Transit - Service Vehicles
Purchase Vacuum Trains Construction $34,734,584 $34,734,584 0% Mar 2015 2018 2018
New York City Transit - Misc./Emergency
Capital Revolving Fund - 2011 Construction $5,000,000 $5,000,000 0% Mar 2011 Mar 2011 Mar 2016 2018
Capital Revolving Fund - 2012 Construction $5,000,000 $5,000,000 0% Apr 2012 Apr 2012 Apr 2017 2018
Capital Revolving Fund - 2013 Construction $5,000,000 $5,000,000 0% Apr 2013 Apr 2013 Apr 2018 2018
Capital Revolving Fund - 2014 Construction $5,000,000 $5,000,000 0% Feb 2014 Feb 2014 2019 2019
All Agency Protective Liability Insurance Deductible Construction $5,000,000 $5,000,000 0% 2010
Owner Controlled Insurance Program Construction $101,436,813 $101,436,813 0% Nov 2012 Nov 2012 Apr 2018 2018
NYCT-Wide Storage Area Network/Disaster Recovery Construction $22,395,195 $22,395,195 0% 2012 Dec 2011 Aug 2012 2018
Concrete Batch Plant Construction $1,290,000 $1,290,000 0% 2012 Jan 2015 2016 2018
Concrete Cylinder Testing Construction $750,000 $750,000 0% 2012 Oct 2014 2016 2018
Asbestos Disposal Construction $913,639 $913,639 0% 2011 Sep 2014 2017 2018
Fire Sprinkler/Alarm Systems at 11 Employee Facilities Construction $26,558,692 $26,167,665 (1%) 2011 Feb 2012 Feb 2014 2018
Groundwater, Soil Remediation Construction $6,500,000 $5,738,227 (12%) 2011 Feb 2013 Feb 2018 2018
Consultant Services - Underground Storage Tank Remediation Construction $6,000,000 $6,761,773 13% 2011 Oct 2012 Oct 2015 2018
Asbestos Removal Construction $9,660,000 $9,660,000 0% 2013 Sep 2014 2016 2018
Asbestos / Lead Air Monitoring Construction $9,120,000 $9,120,000 0% 2013 Sep 2014 2017 2018
Rapid Transit Operations Facilities Hardening Phase 1 Construction $5,902,364 $5,902,364 0% 2010 May 2012 May 2013 2018
Perimeter Hardening at the Power Control Center and 130 Livingston Plaza Construction $10,421,929 $7,923,126 (24%) 2010 Dec 2014 2015
Rehabilitation of Employee Facility at 207th Street on the 8th Av Line Construction $6,650,000 $6,650,000 0% 2010 May 2012 Jul 2013 2018
Livingston Plaza Repairs Construction $27,257,503 $29,661,736 9% 2013 Dec 2014 Sep 2015
Facility Roof Repair/Replacement Phase 4 Construction $16,405,404 $17,020,315 4% 2013 Oct 2015 2017 2018
Rapid Transit Operations Facilities Hardening Phase 2 Construction $11,579,685 $11,579,685 0% 2014 Dec 2015 2016 2018
Number of Projects for New York City Transit = 102
 
Super Storm Sandy - Staten Island Railway
Recovery: Reconstruction of Clifton Car Repair Shop Construction $35,057,174 $35,057,174 0% Dec 2016 Dec 2016 2020
Mitigation: Reconstruction of Clifton Car Repair Shop Construction $167,732,700 $167,732,700 0% Dec 2016 2020
Number of Projects for SIRTOA = 2
 
Staten Island Railway
Staten Island Railway Non-Reporting Blocks Alarms Construction $3,648,658 $2,218,701 (39%) 2014 Oct 2016 2021 2021
Number of Projects for SIRTOA = 1
 
Super Storm Sandy - Track
Flood and Emergency Management Equipment Mitigation Construction $20,000,000 $20,000,000 0% Oct 2014 Nov 2018 Oct 2020
Gateway 11th Ave Extension Construction $5,500,000 $5,500,000 0% * * * *
Super Storm Sandy - Line Structures
Atlantic Ave Tunnels Mitigation Construction $9,900,000 $9,900,000 0% Oct 2014 Oct 2016 May 2018
Super Storm Sandy - Communications & Signals
Restoration of the Long Beach Branch Construction $68,666,958 $68,666,958 0% Sep 2013 Jul 2013 Jan 2018 Sep 2019
Super Storm Sandy - Shops And Yards
West Side Storage Yard Restoration Construction $43,300,000 $41,050,000 (5%) Mar 2013 Oct 2013 Feb 2020 Apr 2019
Long Island City Yard Restoration Construction $20,533,346 $24,268,787 18% Oct 2013 Aug 2014 Jan 2017 Sep 2020
Long Island City Yard Resiliency Construction $1,272,723 $3,692,282 190% Oct 2013 Aug 2014 Jan 2017 Jan 2019
Super Storm Sandy - Power
Long Beach Branch Substation Replacement. Construction $50,191,902 $50,191,902 0% Mar 2013 Sep 2013 Nov 2018 Jan 2018
First Avenue Substation Restoration Construction $8,429,861 $8,429,861 0% Sep 2013 Sep 2013 Oct 2016 Jul 2017
Number of Projects for Long Island Rail Road = 9
 
Long Island Rail Road - Rolling Stock
Purchase 92 M-9 electric cars. Construction $354,751,200 $365,451,200 3% 2011 Sep 2013 Jan 2017 Apr 2018
Long Island Rail Road - Stations
Wantagh Station Platform Replacement Construction $22,467,816 $23,425,478 4% 2012 Mar 2016 Dec 2017 Sep 2018
East Side Access / Grand Central Terminal Support Construction $8,331,501 $8,331,501 0% 2014 Oct 2013 Dec 2015 Dec 2013
Long Island Rail Road - Track
East River Tunnel Track Replacement Construction $43,200,000 $43,200,000 0% Mar 2012 Mar 2012 Jan 2018 Oct 2016
Jamaica Capacity Improvements - Phase One Construction $301,653,240 $301,653,240 0% 2011 May 2014 Jan 2014 Oct 2019
Massapequa Pocket Track Construction $19,600,000 $19,600,000 0% Apr 2012 Apr 2012 Jun 2016 Apr 2019
Extend Great Neck Pocket Track Construction $25,400,000 $25,400,000 0% 2011 Oct 2014 Jun 2015 Dec 2019
Second Track Farmingdale to Ronkonkoma - Phase 1 Construction $137,200,000 $137,200,000 0% Dec 2013 Dec 2013 May 2014 Nov 2018
Long Island Rail Road - Line Structures
150th Street - Jamaica Bridge Rehabilitation Construction $21,860,000 $17,245,000 (21%) Jan 2014 Mar 2013 Jan 2016 Jan 2017
Long Island Rail Road - Communications And Signals
Private Branch Exchange / Wayside Phone systems replacement - Phase 1 Construction $9,209,574 $9,209,574 0% 2010 Sep 2011 Jan 2017 Oct 2016
Radio Coverage Improvements Construction $5,760,467 $5,760,467 0% 2010 Feb 2012 Jun 2015 Dec 2016
Positive Train Control (PTC) Construction $235,343,968 $235,343,968 0% Mar 2012 Aug 2010 Dec 2015 Dec 2018
Speonk to Montauk Signalization Construction $79,056,032 $79,056,032 0% 2010 Jun 2011 Jan 2016 Nov 2017
Centralized Train Control Construction $17,900,000 $17,900,000 0% 2011 Dec 2012 Jan 2014 Sep 2018
Long Island Rail Road - Shops And Yards
Hillside Facility Roof Renewals Construction $6,000,000 $6,000,000 0% Oct 2013 Oct 2013 Jan 2013 Jan 2016
New Mid Suffolk Electric Yard Construction $76,600,000 $80,450,000 5% 2011 Sep 2017 Sep 2016 Mar 2020
Employee Facilities Renewals Construction $11,029,343 $11,029,343 0% Nov 2011 Nov 2011 Jan 2013 Mar 2017
Long Island Rail Road - Power
Replacement of Port Washington Substation Construction $26,159,452 $26,159,452 0% Apr 2013 Oct 2016 Mar 2017 Jul 2018
Replacement of Richmond Hill Substation Construction $16,617,791 $16,617,791 0% Oct 2015 Oct 2015 2019 Feb 2020
Long Island Rail Road - Miscellaneous
Speonk Yard Metal Treatment System Construction $2,000,000 $2,000,000 0% Apr 2017 Apr 2017 Dec 2017 Dec 2017
Number of Projects for Long Island Rail Road = 20
 
Super Storm Sandy - Track And Structures
Right of Way Restoration Construction $8,000,000 $8,000,000 0% Mar 2013 May 2013 Dec 2015 Jan 2019
Rail Vacuum Mitigation Construction $6,000,000 $6,000,000 0% Dec 2015 Dec 2016 Aug 2018
Super Storm Sandy - Communications And Signals
Communications & Signal Infrastructure Restoration Phase 1 Construction $46,556,376 $46,556,376 0% 2014 May 2015 Jun 2016 Mar 2019
Communications & Signal Infrastructure Restoration Phase 2 Construction $35,020,659 $35,020,659 0% Nov 2016 Nov 2016 2016 Mar 2021
Power and Signals Mitigation Construction $50,000,000 $50,000,000 0% May 2015 Jul 2019 Mar 2021
Hudson Line Power and Signal Resiliency Construction $31,000,000 $31,000,000 0% May 2015 May 2015 Jul 2019 Mar 2021
Super Storm Sandy - Power
Power Infrastructure Restoration Phase 1 Construction $88,058,310 $89,173,783 1% 2014 May 2015 Jun 2016 Mar 2019
Power Infrastructure Restoration Phase 2 Construction $72,465,602 $72,465,602 0% Nov 2016 Nov 2016 2018 Mar 2021
Power Infrastructure Restoration - Substations Construction $44,403,381 $44,362,600 0% Dec 2014 Dec 2014 Jan 2016 Sep 2018
Power Infrastructure Restoration - Harlem River Lift Bridge Construction $7,120,000 $7,663,410 8% Oct 2014 Oct 2014 Apr 2016 Jan 2019
Number of Projects for Metro North Railroad = 10
 
Metro-North Railroad - Rolling Stock
EMU Replacement / Repair Construction $24,969,000 $24,969,000 0% 2010 Aug 2006 May 2014 Jan 2021
Purchase M-8 Series Cars for the New Haven Line Construction $220,500,000 $220,500,000 0% 2010 Aug 2006 May 2014 Jan 2021
Metro-North Railroad - Stations
Grand Central Terminal Leaks Remediation Construction $18,554,060 $18,554,060 0% 2012 Dec 2013 Dec 2015 May 2018
Grand Central Terminal Utility System Improvements Construction $33,261,158 $33,261,158 0% Oct 2013 Oct 2013 Jan 2016 Jan 2019
New Fare Payment System Construction $0 $2,644,000 0% 2010 Nov 2017 Jun 2014 Sep 2022
Metro-North Railroad - Track And Structures
Mainline/High Speed Turnout Replacement Construction $60,762,600 $60,500,332 0% Aug 2010 Aug 2010 Dec 2014 Apr 2019
Bridge Walkways Installation Construction $842,335 $842,335 0% Dec 2010 Dec 2010 Dec 2014 Mar 2018
Repair/Replacement of Undergrade Bridges Construction $24,892,369 $24,892,369 0% 2010 Dec 2012 Apr 2015 Dec 2018
Repair/Replace East of Hudson Overhead Bridges Construction $18,900,000 $18,900,000 0% 2011 Sep 2017 Apr 2015 Jan 2021
Repair/Replace Undergrade Bridges on the West of Hudson, Port Jervis Line Construction $6,198,802 $6,198,802 0% 2010 Sep 2014 Jan 2015 Jan 2019
Metro-North Railroad - Communications And Signals
Positive Train Control Construction $187,080,000 $187,080,000 0% 2010 Jul 2012 Dec 2015 Dec 2018
Upgrade West of Hudson Signal System Construction $67,600,000 $67,600,000 0% 2011 Jul 2012 Dec 2015 Oct 2020
Replace Fiber/Communication & Signals Cables Construction $4,245,376 $4,245,376 0% 2012 Dec 2010 Dec 2013 Nov 2017
Replace Field Code System at Mott Haven Construction $1,424,317 $1,424,317 0% 2010 Apr 2015 Mar 2013 Dec 2019
New Haven Line Signal Improvements Construction $3,620,000 $3,620,000 0% Aug 2013 Aug 2013 Feb 2014 Aug 2016
Metro-North Railroad - Power
Replace and Upgrade Substation Bridge 23 Construction $41,734,052 $41,734,052 0% 2011 Jul 2012 Nov 2013 Oct 2018
Harlem and Hudson Line Power Improvements Construction $33,738,691 $33,738,691 0% 2012 Mar 2014 Jan 2014 Mar 2019
Replace 3rd Rail Infrastructure in the Park Avenue Tunnel Construction $6,134,220 $6,134,220 0% 2010 Jan 2014 Dec 2014 May 2017
Metro-North Railroad - Shops And Yards
Harmon Shop Replacement Program Construction $315,590,606 $315,590,606 0% 2012 Oct 2011 Dec 2016 Jun 2018
Metro-North Railroad - Miscellaneous
System wide Lead/Asbestos Abatement Construction $250,000 $250,000 0% 2010 Nov 2015 Aug 2015 Jan 2019
Environmental Remediation Construction $450,000 $450,000 0% 2010 Jul 2011 Aug 2015 Jan 2019
Railroad Protective Liability Construction $714,029 $714,029 0% 2010 Feb 2011 Jun 2015 Mar 2018
Number of Projects for Metro-North Railroad = 22
 
Bridges and Tunnels - Structures
This project will construct miscellaneous structural steel repairs at various locations on the Marine Parkway Bridge. Construction $27,950,972 $28,454,328 2% Sep 2015 Dec 2015 Sep 2018 Dec 2018
Rehabilitation of Tunnel Walls, Ceiling Repair and Leak Control - Queens Midtown Tunnel Construction $62,741,544 $62,741,544 0% 2014 Apr 2015 Mar 2017 Jul 2018
Miscellaneous steel and concrete rehabilitation - Manhattan approach ramps of the Robert F Kennedy Bridge Construction $102,947,301 $102,947,301 0% 2013 Dec 2014 Mar 2017 Oct 2017
Bridges and Tunnels - Roadways And Decks
Replacement of Brooklyn Plaza structural slab - Brooklyn-Battery Tunnel Construction $18,638,132 $18,638,132 0% 2013 Dec 2014 Sep 2015 Nov 2017
Replacement of the Bronx and Manhattan Toll Plaza deck area, utility relocation, personnel and facilities relocation - Robert F Kennedy Bridge Construction $307,655,058 $317,663,519 3% 2013 Dec 2014 Mar 2019 Jun 2019
Rehabilitate Ramp connecting Bruckner Expressway to RFK Bridge Construction $15,721,762 $23,000,000 46% Dec 2017 Apr 2020
Bridges and Tunnels - Toll Plazas & Traffic Mgmt
Installation of weather information Systems at the four major bridges Construction $3,510,705 $3,510,705 0% 2012 Dec 2016 Dec 2014 2018
Second Generation E-ZPass in-lane subsystem evaluation and modernization Construction $16,110,327 $16,110,327 0% 2012 Jun 2010 Dec 2015 Dec 2016
Bridges and Tunnels - Utilities
Rehabilitation of the Programmable Logic Controller and electrical and mechanical systems of the Marine Parkway Bridge Lift Span Construction $10,164,452 $10,164,452 0% 2013 Nov 2015 Sep 2015 Jun 2018
Rehabilitation of the Programmable Logic Controller and electrical and mechanical systems of the Marine Parkway Bridge Lift Span Construction $38,842,973 $41,187,148 6% Sep 2015 Dec 2015 Sep 2018 Dec 2018
Tunnel Ventilation Building Electrical Upgrade Replace electrical switchgear and fan motor control Equipment - Queens Midtown Tunnel Construction $56,178,852 $56,178,852 0% Dec 2012 Dec 2012 May 2016 Jul 2018
Bridges and Tunnels - Structural Painting
Zone and Spot Paint Rockaway Point Boulevard Bridge, Jacob Riis Pedestrian Bridge, and Marine Parkway Bridge Construction $27,467,576 $27,467,576 0% Sep 2015 Dec 2015 Sep 2018 Dec 2018
Number of Projects for Bridges and Tunnels = 12
 
Super Storm Sandy - Structures
Restoration of Queens Midtown Tunnel after Super Storm Sandy Construction $145,537,089 $145,537,089 0% Nov 2014 Apr 2015 Nov 2018 Jul 2018
Hugh Carey Tunnel mitigation - perimeter work Construction $36,248,968 $36,248,968 0% Dec 2016 Dec 2018
Queens Midtown Tunnel mitigation - flood gates and other Construction $29,254,989 $29,254,989 0% Dec 2016 Jan 2016 Dec 2018
Super Storm Sandy - Roadways & Decks
Restore Queens Midtown Tunnel roadway after Super Storm Sandy Construction $1,467,743 $1,467,743 0% Nov 2014 Apr 2015 Nov 2018 Jul 2018
Super Storm Sandy - Utilities
Restoration of Marine Parkway Bridge -electrical equipment damaged by Super Storm Sandy Construction $8,433,615 $8,433,615 0% Jul 2014 Nov 2015 Jul 2016 Jun 2018
Restoration of Cross Bay Bridge Utilities damaged by Super Storm Sandy Construction $13,470,419 $13,470,419 0% Jun 2014 Nov 2015 Jun 2016 Jun 2018
Restoration of Queens Midtown Tunnel - Control/Communications Systems CCTV Traffic Signals after Super Storm Sandy Construction $105,871,989 $105,871,989 0% Nov 2014 Apr 2015 Nov 2018 Jul 2018
Raising of revenue control equipment at the Queens Midtown Tunnel Service Building above the 500-year flood elevation. Construction $1,215,000 $1,215,000 0% Nov 2014 Oct 2014 Nov 2016 Jul 2018
Super Storm Sandy - Buildings & Utilities
Environmental clean-up at Queens Midtown Tunnel after Super Storm Sandy Construction $10,805,889 $10,805,889 0% Sep 2013 Feb 2015 Nov 2018 Jul 2018
Hugh Carey Tunnel - Raise seawalls at the Governors Island Vent Building Construction $31,030,077 $30,876,047 0% Dec 2016 Dec 2018
Number of Projects for MTA Bridges & Tunnels = 10
 
Super Storm Sandy - Bus Company Projects
Recovery: Far Rockaway Depot Construction $15,000,000 $15,000,000 0% 2014 Aug 2016 2015 2018
Number of Projects for MTA Bus Company = 1
 
MTA Bus Company - Bus Company Projects
Project Administration and Engineering Support Services Construction $17,590,000 $17,619,324 0% 2011 Mar 2014 2018 2018
Replace 2 Bus Washers at Spring Creek Depot (SBFP) Construction $2,700,000 $3,367,800 25% 2014 Jun 2017 2017 2018
Construction Management Services Construction $8,695,002 $8,692,745 0% 2011 Mar 2015 2019
New Bus Command Center Building Construction $17,119,402 $17,119,402 0% 2014 Jun 2015 2016 2018
Replacement of Bus Radio System Construction $27,920,675 $27,920,675 0% 2014 Mar 2016 2018 2021
Number of Projects for MTA Bus Company = 5
 
MTA Interagency - MTA BSC / Facilities Rehab
Biltmore Room Connection Construction $21,841,898 $21,841,898 0% Sep 2013 Feb 2015 Jan 2017 2019
MTA Interagency - MTA Planning
MTA Core Long-Range Planning Support for Capital Needs Construction $25,853,988 $27,664,364 7% 2010 2011 2016 2019
MTA Long-Range Travel Corridor Research and Planning Support Construction $8,500,000 $6,689,624 (21%) 2010 2017 2016 2019
Number of Projects for MTA Interagency = 3
 
Capital Construction - East Side Access
ESA: Program Management Construction $68,379,918 $73,774,457 8% 2011 Jan 2010 Sep 2016 Dec 2017
ESA: Engineering and Design Construction $85,427,401 $85,427,401 0% 2011 Sep 2016
ESA: MTA Management Construction $28,406,928 $28,606,928 1% 2011 Jan 2010 Sep 2016 Dec 2018
ESA: Metro-North Railroad Force Account Support for Manhattan Structural work Construction $16,681,015 $16,681,015 0% Jan 2011 Jan 2011 Oct 2012 Jun 2020
ESA: Owner-Controlled Insurance Program (OCIP) Construction $112,445,249 $79,874,195 (29%) 2011 Jan 2010 Sep 2016 Dec 2017
ESA: Construction Management Construction $230,402,608 $223,724,392 (3%) 2011 Jan 2010 Sep 2016 Dec 2022
ESA: Vertical Circulation Equipment - Elevators and Escalators Construction $3,709,168 $3,709,168 0% 2011 Sep 2010 Apr 2015 Jun 2020
ESA: General Conditions Construction $49,459,380 $49,459,380 0% 2011 Jan 2010 Sep 2016 Dec 2022
ESA: Harold Interlocking Force Account Construction $109,230,631 $124,663,866 14% 2011 Jun 2013 Jan 2016 Dec 2022
ESA: Queens Plaza Substation and Structures Construction $257,981,267 $259,484,950 1% Aug 2011 Aug 2011 Feb 2014 Jun 2018
ESA: Mid-Day Storage Yard Facility CILs Construction $19,423,929 $22,323,929 15% 2012 Jan 2016 Oct 2014 Dec 2020
ESA: Harold Structures - Part 3A Construction $77,599,894 $79,479,930 2% 2011 Dec 2013 Dec 2013 Nov 2017
ESA: Amtrak Access and Protection Construction Support Construction $17,517,596 $22,869,301 31% 2011 Jan 2010 Sep 2016 Dec 2022
ESA: Long Island Rail Road Access and Protection Construction Support Construction $5,730,381 $9,882,358 72% 2011 Jan 2010 Sep 2016 Dec 2022
ESA: System Testing and Commissioning Construction $4,760,179 $4,760,179 0% 2011 Dec 2018 Sep 2016 Dec 2022
ESA: Real Estate Construction $57,871,691 $57,839,033 0% 2011 Jan 2010 Sep 2016 Dec 2022
ESA: 250 HZ Track Circuit Construction $17,843,795 $17,843,795 0% Jun 2011 Apr 2017 Oct 2014 Mar 2022
ESA: Communication, Control, Tunnel Ventilation and Facility Power Systems Construction $368,814,438 $368,814,438 0% Mar 2012 Mar 2014 Jul 2015 Jan 2021
ESA: Signal Equipment Procurement Construction $21,835,022 $21,835,022 0% Apr 2012 Jun 2014 May 2014 Jan 2021
ESA: Force Account Warehouse Construction $3,405,498 $3,405,498 0% 2012 Jun 2013 2019 Dec 2022
ESA: Manhattan Utilities Relocations Construction $17,720,901 $17,720,901 0% Oct 2012 Oct 2012 2019 Jun 2020
ESA: Manhattan North Structures Construction $361,638,562 $361,638,562 0% Mar 2014 Mar 2014 Nov 2016 Jun 2018
ESA: Traction Power Systems Construction $79,717,772 $79,717,772 0% Sep 2014 Oct 2014 Dec 2019 Jan 2021
ESA: GCT Concourse and Facilities Fit-Out Construction $434,174,159 $434,174,159 0% Nov 2014 Feb 2015 Jul 2019 May 2020
ESA: Early work for the 48th Street Entrance at 415 Madison Avenue Construction $11,867,875 $14,052,660 18% Jun 2015 Feb 2016 May 2018 Dec 2022
ESA: Building Owner Work Construction $275,000 $570,000 107% Jul 2015 Jun 2016 Dec 2019 Dec 2022
Capital Construction - Full Length Second Ave Subway
SAS: Construction Management Construction $74,448,578 $89,858,210 21% Jan 2011 Jan 2011 Dec 2016 Dec 2018
SAS: Concrete Cylinder Testing Construction $633,387 $633,387 0% Jan 2015 Jan 2015 Dec 2016 Dec 2017
SAS: Concrete Batch Testing Construction $481,818 $481,818 0% Jan 2015 Jan 2015 Dec 2016 Dec 2017
SAS: Systems - Power, Signal, Tracks and Communications Construction $16,093,000 $48,387,104 201% Apr 2016 Apr 2016 Dec 2016 Jun 2018
SAS: Station Signage Construction $534,033 $2,686,708 403% May 2016 May 2016 Dec 2016 Dec 2017
SAS: Misc Furnishings Construction $1,808,400 $1,808,400 0% Aug 2016 Aug 2016 Dec 2016 Dec 2017
Capital Construction - Regional Investments
Regional Investment to Support ESA: West Bound Bypass and East Bound Re-Route In-House Work Construction $71,334,701 $91,164,852 28% 2012 Jul 2013 May 2015 Sep 2025
Regional Investment to Support ESA: Loop Interlocking Construction $28,718,450 $24,428,226 (15%) 2012 May 2013 Jun 2016 Sep 2025
Regional Investment to Support ESA: Demo of Amtrak Buildings in Harold Interlocking Construction $27,024,351 $16,261,745 (40%) Oct 2012 Oct 2012 Oct 2014 Aug 2018
Regional Investment to Support ESA: 45th St ADA Elevator Construction $2,800,000 $2,154,930 (23%) Jun 2012 Jun 2012 Dec 2015 Jun 2020
Regional Investment to Support ESA: Owner-Controlled Insurance Program (OCIP) Construction $16,939,198 $16,939,198 0% Jan 2012 Jan 2012 Aug 2019 Sep 2025
Regional Investment to Support ESA: Construction Management Construction $27,974,054 $51,922,267 86% Jan 2012 Jan 2012 Aug 2019 Sep 2025
Regional Investment to Support ESA: Harold Structures - Part 3, East Approach of East Bound Re-Route and other structures Construction $22,067,263 $35,836,122 62% Nov 2014 Aug 2015 Aug 2016 Jun 2017
Capital Construction - Miscellaneous
Miscellaneous Engineering and Program Support Construction $127,446,621 $75,602,881 (41%) Jan 2010 Jan 2010 2016 2019
Number of Projects for Capital Construction = 40