Structures
Feasibility Study for tunnel improvements and modernization of the Brooklyn-Battery and Queens Midtown Tunnels   Complete   $3,365,889 $2,442,288 (27%) 2010 Apr 2011 Aug 2013 Oct 2015
Rehabilitation of tunnel walls Roadway drainage and fire line repair at Brooklyn-Battery Tunnel   Complete   $65,561,692 $65,561,692 0% Dec 2014 Dec 2014 Feb 2017 Mar 2018
Miscellaneous structural rehabilitation: steel and concrete repairs - Bronx Whitestone Bridge   Complete   $3,633,485 $3,633,485 0% Sep 2013 Sep 2013 Aug 2015 Apr 2015
Monitoring, inspection, and testing of the Bronx-Whitestone Bridge's main cable and cable wires   Complete   $2,815,652 $2,815,652 0% 2014 Aug 2013 Dec 2015 Apr 2015
Concrete repairs at the Bronx anchorage of the Bronx-Whitestone Bridge   Complete   $7,663,646 $7,663,646 0% Oct 2012 Oct 2012 Jun 2014 Aug 2014
Rehabilitation of the Concrete Substructure and Underwater Work - Cross-Bay Bridge   Complete   $17,006,619 $17,002,479 0% Nov 2010 Nov 2010 Feb 2013 Dec 2012
Structural Rehabilitation - Phase I - Henry Hudson Bridge   Complete   $8,158,112 $8,158,112 0% 2012 Dec 2011 Feb 2014 Oct 2013
Design for the Replacement of the Lower Level South Approach Deck at Henry Hudson Bridge   Complete   $49,586 $49,586 0% 2012 Nov 2011 Dec 2014 2015
Substructure and underwater scour protection - Marine Parkway Bridge   Complete   $22,389,689 $22,706,029 1% 2012 Nov 2013 Jul 2014 Oct 2015
Miscellaneous Steel Repairs - Marine Parkway Bridge   Complete   $2,512,355 $2,512,355 0% 2012 Jan 2013 Dec 2013 Mar 2015
Structural Rehabilitation of the Entrance and Exit Plazas - Queens Midtown Tunnel   Complete   $16,486,941 $16,486,941 0% 2013 Apr 2015 Jan 2016 Jul 2017
Seismic and wind study for Robert F Kennedy Bridge   Complete   $5,400,000 $5,400,000 0% Dec 2012 Dec 2012 Jul 2014 Jun 2015
Miscellaneous structural repair - Robert F Kennedy Bridge   Complete   $11,171,357 $6,171,357 (45%) Dec 2014 Dec 2014 Dec 2016 Aug 2016
Miscellaneous structural rehabilitation - Throgs Neck Bridge   Complete   $27,276,854 $27,276,854 0% 2012 Jun 2011 Dec 2015 May 2016
Design only of an anchorage dehumidification system - Throgs Neck Bridge   Complete   $2,179,222 $2,179,222 0% 2012 Jul 2013 Jun 2014 Apr 2015
Steel repairs, concrete rehabilitation and repair/rehabilitation of drainage systems - Verrazano-Narrows Bridge   Complete   $11,064,339 $9,848,748 (11%) Dec 2013 Dec 2013 Dec 2014 May 2017
Roadways And Decks
Deck Replacement - the Queens Elevated and on-grade approach of the Bronx-Whitestone Bridge   Complete   $132,314,734 $130,050,383 (2%) Jul 2011 Jul 2011 Aug 2015 Jan 2015
Replacement of the Upper Level sidewalk, curb stringers, and roadway lighting - Henry Hudson Bridge   Complete   $39,157,763 $39,157,763 0% Dec 2010 Dec 2010 Sep 2013 Jul 2013
Replacement of the Upper and Lower Level Toll Plaza and Southbound Approach - Henry Hudson Bridge   Complete   $50,954,491 $50,954,491 0% Dec 2014 Dec 2014 Dec 2015 Dec 2016
Rehabilitation of the Rockaway Point Boulevard and Jacob Riis Park pedestrian bridges   Complete   $11,052,001 $11,052,001 0% 2013 Jan 2015 Aug 2015 Jun 2016
Demolition and reconstruction of the Manhattan to Queens ramp of the Robert F Kennedy Bridge   Complete   $53,823,592 $53,823,592 0% Mar 2012 Jul 2012 May 2014 Aug 2014
Replacement of the surface layer on the orthotropic deck sections of the Robert F Kennedy Bridge   Complete   $10,338,105 $10,338,105 0% 2010 Feb 2011 Feb 2013 Oct 2011
Interim Deck Repairs - Manhattan Toll Plaza Deck - Robert F Kennedy Bridge   Complete   $46,563,484 $46,563,484 0% 2013 Oct 2014 Mar 2019 Oct 2015
Phase A of the suspended span deck replacement - Throgs Neck Bridge - Utility relocation and prototype construction   Complete   $21,491,945 $21,491,945 0% 2013 May 2012 Feb 2016 Nov 2013
Phase B of the rehabilitation of the Orthotropic Deck - Throgs Neck Bridge   Complete   $16,670,822 $16,670,822 0% Jul 2011 Jul 2011 Jan 2014 Dec 2014
Toll Plaza improvements at eastbound and westbound ramps of Verrazano Narrows Bridge Eastbound mainline rehabilitation at Verrazano-Narrows Bridge   Complete   $63,740,560 $63,740,560 0% Sep 2011 Sep 2011 May 2015 Nov 2014
Replacement of the upper level suspended span deck - Verrazano-Narrows Bridge   Complete   $352,581,037 $347,626,708 (1%) Nov 2012 Nov 2012 Nov 2017 May 2017
Toll Plazas & Traffic Mgmt
Advanced Traffic Detection / Management System   Complete   $11,210 $11,210 0% 2012 Nov 2014
Utilities
Replacement of the electrical switchgear and equipment at Brooklyn-Battery Tunnel   Complete   $51,580,239 $51,580,239 0% Dec 2010 Dec 2010 Sep 2014 Sep 2014
Installation of New Necklace Lighting System and Acoustic Monitoring System - Bronx-Whitestone Bridge   Complete   $12,104,099 $12,104,099 0% 2012 Jul 2013 Dec 2013 Nov 2015
Design for the replacement of the utilities within the Queens Midtown Tunnel Facility Supervisory Control System   Complete   $4,305,012 $2,011,429 (53%) 2012 Apr 2014 Sep 2014 Dec 2016
Rehabilitation of Electrical Substation #1 at the Verrazano-Narrows Bridge   Complete   $16,634,707 $16,634,707 0% 2013 Feb 2014 May 2015 Jun 2016
Buildings And Sites
Agency-wide hazardous materials abatement   Complete   $2,345,255 $2,345,255 0% 2011 Apr 2014 Jan 2015 Dec 2014
Service Building rehabilitation at Brooklyn-Battery Tunnel   Complete   $9,930,358 $9,930,358 0% 2013 Jul 2014 Jan 2014 Jun 2016
Miscellaneous repairs at the Battery Parking Garage   Complete   $629,812 $629,812 0% 2013 Oct 2014 Jan 2015 Oct 2016
Miscellaneous
MTA Independent Engineering services   Complete   $2,545,186 $2,545,186 0% 2014 Apr 2011 Jan 2015 2015
All Agency protective liability insurance   Complete   $6,553,090 $6,553,090 0% Nov 2010 Nov 2010 Jun 2015 2015
Program Administration   Complete   $13,235,156 $13,235,156 0% Aug 2010 Aug 2010 Jan 2015 Jan 2015
Small Business Mentoring Program   Complete   $0 $0 0% 2011
Structural Painting
Miscellaneous agency wide painting   Complete   $0 $0 0% Jul 2014 Jul 2014 Dec 2014 Dec 2015
Paint curb stringers at Henry Hudson Bridge   Complete   $756,056 $756,056 0% Dec 2010 Dec 2010 Sep 2013 Sep 2013
Paint steel members, toll plaza deck and approach ramps at Robert F Kennedy Bridge   Complete   $23,022,673 $19,948,501 (13%) 2013 Dec 2014 Mar 2019 Jun 2019
Paint Bronx approach of Throgs Neck Bridge   Complete   $37,278,677 $37,278,677 0% Jul 2011 Jul 2011 Jan 2014 Dec 2014
Paint - Steel Members of the Suspended Span Deck - Throgs Neck Bridge   Complete   $6,126,252 $6,126,252 0% 2010 Jun 2011 Jul 2013 Dec 2013
Paint structural steel of Bronx and Queens tower fender systems at Throgs Neck Bridge   Complete   $6,959,998 $6,959,998 0% Mar 2010 Mar 2010 Mar 2012 Mar 2012
Paint Brooklyn and Staten Island lower level ramps at Verrazano Narrows Bridge   Complete   $15,893,313 $15,893,313 0% Dec 2013 Dec 2013 Dec 2014 May 2017
Paint - Upper Level Superstructure - Verrazano-Narrows Bridge   Complete   $32,908,184 $31,817,729 (3%) Nov 2012 Nov 2012 Apr 2016 May 2017
Paint towers below the roadway level at Verrazano-Narrows Bridge   Complete   $23,472,213 $23,472,213 0% Aug 2010 Aug 2010 Oct 2012 Oct 2012