Capital Plan 2010 - 2014  
Bridges and Tunnels  
Buildings And Sites   Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Agency-Wide
Agency-wide hazardous materials abatement   Complete   $2,345,255 $2,345,255 0% 2011 Apr 2014 Jan 2015 Dec 2014
Brooklyn-Battery Tunnel
Service Building rehabilitation at Brooklyn-Battery Tunnel   Complete   $9,930,358 $9,930,358 0% 2013 Jul 2014 Jan 2014 Jun 2016
Miscellaneous repairs at the Battery Parking Garage   Complete   $629,812 $629,812 0% 2013 Oct 2014 Jan 2015 Oct 2016
Number of Projects for MTA Bridges & Tunnels = 3