Capital Plan 2010 - 2014 
Bridges & Tunnels 
Structures   Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Agency-Wide
Feasibility Study for tunnel improvements and modernization of the Brooklyn-Battery and Queens Midtown Tunnels   Complete   $3,365,889 $2,811,941 (16%) 2010 Apr 2011 Aug 2013 Oct 2015
Brooklyn-Battery Tunnel
Rehabilitation of tunnel walls Roadway drainage and fire line repair at Brooklyn-Battery Tunnel Construction $65,561,692 $65,561,692 0% Dec 2014 Dec 2014 Feb 2017 Mar 2018
Bronx-Whitestone Bridge
Tower and Pier Fender Protection System - Bronx-Whitestone Bridge   Design    $3,629,249 $3,629,249 0% 2012 Sep 2013 Sep 2013 Jun 2016
Miscellaneous structural rehabilitation: steel and concrete repairs - Bronx Whitestone Bridge   Complete   $3,633,485 $3,633,485 0% Sep 2013 Sep 2013 Aug 2015 Apr 2015
Monitoring, inspection, and testing of the Bronx-Whitestone Bridge's main cable and cable wires   Complete   $2,815,652 $2,815,652 0% 2014 Aug 2013 Dec 2015 Apr 2015
Concrete repairs at the Bronx anchorage of the Bronx-Whitestone Bridge   Complete   $7,663,646 $7,663,646 0% Oct 2012 Oct 2012 Jun 2014 Aug 2014
Cross Bay Bridge
Rehabilitation of the Concrete Substructure and Underwater Work - Cross-Bay Bridge   Complete   $17,006,619 $17,002,479 0% Nov 2010 Nov 2010 Feb 2013 Dec 2012
Henry Hudson Bridge
Structural Rehabilitation - Phase I - Henry Hudson Bridge   Complete   $8,158,112 $8,158,112 0% 2012 Dec 2011 Feb 2014 Oct 2013
Design for the Replacement of the Lower Level South Approach Deck at Henry Hudson Bridge   Complete   $49,586 $49,586 0% 2012 Nov 2011 Dec 2014 2015
Skewbacks retrofit - Henry Hudson Bridge   Design    $5,730,000 $5,730,000 0% Nov 2013 Nov 2013 Jun 2014 Mar 2016
Marine Parkway Bridge
Substructure and underwater scour protection - Marine Parkway Bridge   Complete   $22,389,689 $22,706,029 1% 2012 Nov 2013 Jul 2014 Oct 2015
Miscellaneous Steel Repairs - Marine Parkway Bridge   Complete   $2,512,355 $2,512,355 0% 2012 Jan 2013 Dec 2013 Mar 2015
This project will construct miscellaneous structural steel repairs at various locations on the Marine Parkway Bridge. Construction $27,950,972 $28,454,328 2% Sep 2015 Dec 2015 Sep 2018 Dec 2018
Queens Midtown Tunnel
Structural Rehabilitation of the Entrance and Exit Plazas - Queens Midtown Tunnel   Complete   $16,486,941 $16,486,941 0% 2013 Apr 2015 Jan 2016 Jul 2017
Rehabilitation of Tunnel Walls, Ceiling Repair and Leak Control - Queens Midtown Tunnel Construction $62,741,544 $62,741,544 0% 2014 Apr 2015 Mar 2017 Jul 2018
Robert F. Kennedy Bridge
Seismic and wind study for Robert F Kennedy Bridge   Complete   $5,400,000 $5,400,000 0% Dec 2012 Dec 2012 Jul 2014 Jun 2015
Miscellaneous steel and concrete rehabilitation - Manhattan approach ramps of the Robert F Kennedy Bridge   Complete   $102,947,301 $102,947,301 0% 2013 Dec 2014 Mar 2017 Oct 2017
Miscellaneous structural repair - Robert F Kennedy Bridge   Complete   $11,171,357 $6,171,357 (45%) Dec 2014 Dec 2014 Dec 2016 Aug 2016
Throgs Neck Bridge
Miscellaneous structural rehabilitation - Throgs Neck Bridge   Complete   $27,276,854 $27,276,854 0% 2012 Jun 2011 Dec 2015 May 2016
Design only of an anchorage dehumidification system - Throgs Neck Bridge   Complete   $2,179,222 $2,179,222 0% 2012 Jul 2013 Jun 2014 Apr 2015
Verrazano-Narrows Bridge
Verrazano-Narrows Bridge main cable testing   Design    $5,356,046 $5,356,046 0% Oct 2014 Oct 2014 Dec 2015 Oct 2019
Steel repairs, concrete rehabilitation and repair/rehabilitation of drainage systems - Verrazano-Narrows Bridge   Complete   $11,064,339 $9,848,748 (11%) Dec 2013 Dec 2013 Dec 2014 May 2017
Number of Projects for MTA Bridges & Tunnels = 22