Feasibility Study for tunnel improvements and modernization of the Brooklyn-Battery and Queens Midtown Tunnels |
 |
Complete |
$3,365,889 |
$2,811,941 |
(16%) |
 |
2010 |
Apr 2011 |
Aug 2013 |
Oct 2015 |
|
Rehabilitation of tunnel walls Roadway drainage and fire line repair at Brooklyn-Battery Tunnel |
 |
Construction |
$65,561,692 |
$65,561,692 |
0% |
 |
Dec 2014 |
Dec 2014 |
Feb 2017 |
Mar 2018 |
|
Tower and Pier Fender Protection System - Bronx-Whitestone Bridge |
 |
Design |
$3,629,249 |
$3,629,249 |
0% |
 |
2012 |
Sep 2013 |
Sep 2013 |
Jun 2016 |
Miscellaneous structural rehabilitation: steel and concrete repairs - Bronx Whitestone Bridge |
 |
Complete |
$3,633,485 |
$3,633,485 |
0% |
 |
Sep 2013 |
Sep 2013 |
Aug 2015 |
Apr 2015 |
Monitoring, inspection, and testing of the Bronx-Whitestone Bridge's main cable and cable wires |
 |
Complete |
$2,815,652 |
$2,815,652 |
0% |
 |
2014 |
Aug 2013 |
Dec 2015 |
Apr 2015 |
Concrete repairs at the Bronx anchorage of the Bronx-Whitestone Bridge |
 |
Complete |
$7,663,646 |
$7,663,646 |
0% |
 |
Oct 2012 |
Oct 2012 |
Jun 2014 |
Aug 2014 |
|
Rehabilitation of the Concrete Substructure and Underwater Work - Cross-Bay Bridge |
 |
Complete |
$17,006,619 |
$17,002,479 |
0% |
 |
Nov 2010 |
Nov 2010 |
Feb 2013 |
Dec 2012 |
|
Structural Rehabilitation - Phase I - Henry Hudson Bridge |
 |
Complete |
$8,158,112 |
$8,158,112 |
0% |
 |
2012 |
Dec 2011 |
Feb 2014 |
Oct 2013 |
Design for the Replacement of the Lower Level South Approach Deck at Henry Hudson Bridge |
 |
Complete |
$49,586 |
$49,586 |
0% |
 |
2012 |
Nov 2011 |
Dec 2014 |
2015 |
Skewbacks retrofit - Henry Hudson Bridge |
 |
Design |
$5,730,000 |
$5,730,000 |
0% |
 |
Nov 2013 |
Nov 2013 |
Jun 2014 |
Mar 2016 |
|
Substructure and underwater scour protection - Marine Parkway Bridge |
 |
Complete |
$22,389,689 |
$22,706,029 |
1% |
 |
2012 |
Nov 2013 |
Jul 2014 |
Oct 2015 |
Miscellaneous Steel Repairs - Marine Parkway Bridge |
 |
Complete |
$2,512,355 |
$2,512,355 |
0% |
 |
2012 |
Jan 2013 |
Dec 2013 |
Mar 2015 |
This project will construct miscellaneous structural steel repairs at various locations on the Marine Parkway Bridge. |
 |
Construction |
$27,950,972 |
$28,454,328 |
2% |
 |
Sep 2015 |
Dec 2015 |
Sep 2018 |
Dec 2018 |
|
Structural Rehabilitation of the Entrance and Exit Plazas - Queens Midtown Tunnel |
 |
Complete |
$16,486,941 |
$16,486,941 |
0% |
 |
2013 |
Apr 2015 |
Jan 2016 |
Jul 2017 |
Rehabilitation of Tunnel Walls, Ceiling Repair and Leak Control - Queens Midtown Tunnel |
 |
Construction |
$62,741,544 |
$62,741,544 |
0% |
 |
2014 |
Apr 2015 |
Mar 2017 |
Jul 2018 |
|
Seismic and wind study for Robert F Kennedy Bridge |
 |
Complete |
$5,400,000 |
$5,400,000 |
0% |
 |
Dec 2012 |
Dec 2012 |
Jul 2014 |
Jun 2015 |
Miscellaneous steel and concrete rehabilitation - Manhattan approach ramps of the Robert F Kennedy Bridge |
 |
Complete |
$102,947,301 |
$102,947,301 |
0% |
 |
2013 |
Dec 2014 |
Mar 2017 |
Oct 2017 |
Miscellaneous structural repair - Robert F Kennedy Bridge |
 |
Complete |
$11,171,357 |
$6,171,357 |
(45%) |
 |
Dec 2014 |
Dec 2014 |
Dec 2016 |
Aug 2016 |
|
Miscellaneous structural rehabilitation - Throgs Neck Bridge |
 |
Complete |
$27,276,854 |
$27,276,854 |
0% |
 |
2012 |
Jun 2011 |
Dec 2015 |
May 2016 |
Design only of an anchorage dehumidification system - Throgs Neck Bridge |
 |
Complete |
$2,179,222 |
$2,179,222 |
0% |
 |
2012 |
Jul 2013 |
Jun 2014 |
Apr 2015 |
|
Verrazano-Narrows Bridge main cable testing |
 |
Design |
$5,356,046 |
$5,356,046 |
0% |
 |
Oct 2014 |
Oct 2014 |
Dec 2015 |
Oct 2019 |
Steel repairs, concrete rehabilitation and repair/rehabilitation of drainage systems - Verrazano-Narrows Bridge |
 |
Complete |
$11,064,339 |
$9,848,748 |
(11%) |
 |
Dec 2013 |
Dec 2013 |
Dec 2014 |
May 2017 |
Number of Projects for
MTA Bridges & Tunnels
=
22
|
|