Capital Plan 2005 - 2009 
New York City Transit 
Line Structures   Budget  Schedule 


Description


Photos


Phase

Original
Budget


Current
Original
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Line Structure Rehabilitation
Overcoat Bronx Park East to 241st Street - White Plains Road Line   Complete   $21,160,800 $31,609,026 49% Apr 2006 Jun 2008 Jun 2009 Dec 2011
Rehabilitate Culver Viaduct Phase 2   Complete   $113,197,100 $168,657,956 49% Aug 2007 Mar 2009 Sep 2012 Dec 2015
Ocean Parkway Station Viaduct - Brighton Line   Complete   $24,370,400 $32,910,314 35% Jun 2007 May 2006 Dec 2009 May 2011
Overcoat Whitlock Avenue Portal to Pelham Bay Park - Pelham Line   Complete   $21,388,800 $29,123,870 36% Apr 2006 Apr 2007 Apr 2011 Jun 2014
Rockaway Viaduct Phase 2   Complete   $67,949,300 $21,513,123 (68%) May 2008 Oct 2008 Jun 2011 May 2011
Overcoat 103rd Street to Main Street Portal - Flushing Line   Complete   $10,925,200 $27,042,577 148% Apr 2007 Oct 2008 Dec 2010 Dec 2010
Flooding Mitigation: Various Locations   Complete   $90,000,000 $83,679,242 (7%) Mar 2009 Mar 2008 Aug 2010 Mar 2011
Arra Line Structure Projects
Structural Rehabilitation 63rd Street to Bay 50th Street - West End Line   Complete   $41,803,946 $32,725,082 (22%) Aug 2009 Aug 2009 Feb 2012 Jul 2012
Structural Rehabilitation 9th Avenue to 63rd Street - West End Line   Complete   $15,073,273 $13,647,514 (9%) Aug 2009 Aug 2009 Jan 2012 Nov 2012
Number of Projects for New York City Transit = 9