Capital Plan 2005 - 2009 
New York City Transit 
Track   Budget  Schedule 


Description


Photos


Phase

Original
Budget


Current
Original
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Track Rehabilitation
Mainline Track Replacement 2009   Complete   $147,815,300 $186,551,727 26% Jan 2009 Jan 2009 Dec 2009 Dec 2009
Track Force Account 2009   Complete   $35,000,000 $35,000,000 0% Jan 2009 Jun 2009 Dec 2009 Dec 2009
Switch Replacement
30 Mainline Switches In-house 2009   Complete   $45,875,900 $41,627,227 (9%) Jan 2009 Jan 2009 Dec 2009 Dec 2009
Number of Projects for New York City Transit = 3