Capital Plan 2005 - 2009  
Metropolitan Transportation Authority   Budget   Schedule  


Description


Photos


Phase

Original
Budget


Current
Original
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
New York City Transit - Signals And Communications
Communications-Based Train Control Flushing Line Phase 1 Construction $265,583,600 $398,329,006 50% 2007 Jun 2010 Nov 2016 2018
Number of Projects for New York City Transit = 1
 
Long Island Rail Road - Track
Main Line Corridor Improvements -Hicksville North Siding Construction $3,796,061 $46,800,033 1,133% 2015 Jul 2016 Apr 2017 Sep 2019
Main Line Corridor Improvements -Hicksville Station Improvements Construction $4,089,736 $74,391,455 1,719% 2015 Jul 2016 Jan 2020 Aug 2018
Number of Projects for Long Island Rail Road = 2
 
Capital Construction - Second Avenue Subway
Second Avenue Subway: Contract 6: Systems Construction $0 $315,902,027 0% 2009 Jan 2012 May 2016 Jul 2018
Capital Construction - Flushing Line Extension
Construction Management Services for the Extension of #7 Subway Line Construction $60,000,000 $73,935,176 23% 2010 Feb 2007 2013 Apr 2019
Number of Projects for Capital Construction = 2