Capital Plan 2005 - 2009 
Capital Construction  Budget  Schedule 


Description


Photos


Phase

Original
Budget


Current
Original
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Flushing Line Extension
Reserve Funds for Work beyond Running Tunnel for the Extension of the #7 Subway Line   Planning  $1,910,000,000 $2,765,710 (100%) 2006 Dec 2013 2018
Number of Projects for Capital Construction = 1