Capital Plan 2005 - 2009 
Metropolitan Transportation Authority  Budget  Schedule 


Description


Photos


Phase

Original
Budget


Current
Original
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
New York City Transit - Subway Cars
Purchase 23 A Division Cars   Complete   $75,869,200 $116,460,786 54% Dec 2005 May 2010 Jun 2013 Dec 2013
Purchase 382 B Division Cars   Complete   $566,582,300 $821,514,204 45% Jan 2008 Nov 2008 Jun 2010 May 2010
New York City Transit - Buses
747 Standard Buses 2007   Complete   $125,350,000 $435,230,971 247% Jan 2006 Dec 2007 Dec 2008 May 2010
90 Standard Buses 2009   Complete   $61,019,000 $54,701,768 (10%) Jan 2009 Nov 2008 Dec 2010 Apr 2016
54 Express Buses   Complete   $49,000,000 $33,411,189 (32%) Jan 2009 Jul 2012 Sep 2011 Dec 2012
New York City Transit - Passenger Stations
Rehabilitate Avenue M Station - Brighton Line   Complete   $20,769,800 $45,336,974 118% Dec 2005 Oct 2008 Jun 2010 Dec 2011
Rehabilitate Neck Road Station - Brighton Line   Complete   $18,862,000 $35,750,771 90% Dec 2005 Jul 2008 Jun 2010 Dec 2010
Rehabilitate Avenue H Station - Brighton Line   Complete   $22,868,300 $45,143,992 97% Dec 2005 Oct 2008 Jun 2010 Dec 2011
Rehabilitate Avenue J Station - Brighton Line   Complete   $21,323,600 $44,303,131 108% Dec 2005 Oct 2008 Jun 2010 Dec 2011
Rehabilitate Avenue U Station - Brighton Line   Complete   $20,769,800 $38,653,255 86% Dec 2005 Jul 2008 Jun 2010 Dec 2010
Rehabilitate Bleecker Street Station - Lexington Avenue Line   Complete   $9,200,000 $31,071,362 238% Jun 2010 Jul 2008 Nov 2011 Nov 2012
Rehabilitate 59th Street Station - Broadway-7th Avenue Line   Complete   $36,448,600 $46,293,794 27% Jul 2005 Dec 2005 Feb 2009 Apr 2011
Rehabilitate 59th Street Station - 8th Avenue Line   Complete   $56,961,100 $57,516,963 1% Jul 2005 Dec 2005 Feb 2009 Apr 2011
Kings Highway Station - Brighton Line   Complete   $19,077,400 $30,358,759 59% Dec 2005 Oct 2008 Jun 2010 Dec 2011
Newkirk Avenue Plaza Station Phase 2 - Brighton Line   Complete   $22,759,900 $41,188,555 81% Dec 2005 Oct 2008 Jun 2010 Dec 2011
Rehabilitate Jay Street Station - Fulton Line   Complete   $41,794,000 $58,476,163 40% Aug 2006 Mar 2007 Mar 2011 Mar 2011
Rehabilitate 96th Street Station - Broadway-7th Avenue Line   Complete   $51,483,900 $54,861,496 7% Dec 2006 May 2007 Oct 2008 Nov 2010
Rehabilitate Morrison-Sound View Avenue Station - Pelham Line   Complete   $19,211,900 $23,215,633 21% Jan 2009 Aug 2009 Jan 2012 Dec 2011
Rehabilitate Parkchester-E 177th Street Station - Pelham Line   Complete   $21,668,300 $31,846,876 47% Jan 2009 Aug 2009 Jan 2012 Dec 2011
Rehabilitate Elder Avenue Station - Pelham Line   Complete   $15,966,300 $21,388,490 34% Jan 2009 Aug 2009 Jan 2012 Dec 2011
Rehabilitate Whitlock Avenue Station - Pelham Line   Complete   $14,369,000 $22,332,144 55% Jan 2009 Aug 2009 Jan 2012 Dec 2011
Rehabilitate Beach 67th Street Station - Rockaway Line   Complete   $6,850,100 $24,717,334 261% May 2008 Jan 2009 Sep 2011 Apr 2013
Rehabilitate Beach 60th Street Station - Rockaway Line   Complete   $7,044,900 $18,310,163 160% May 2008 Jan 2009 Sep 2011 Apr 2013
Rehabilitate Beach 44th Street Station - Rockaway Line   Complete   $6,929,000 $17,790,604 157% May 2008 Jan 2009 Sep 2011 Apr 2013
Rehabilitate Beach 36th Street Station - Rockaway Line   Complete   $6,593,100 $17,083,187 159% May 2008 Jan 2009 Sep 2011 Apr 2013
Rehabilitate Beach 25th Street Station - Rockaway Line   Complete   $6,551,100 $17,655,748 170% May 2008 Jan 2009 Sep 2011 Apr 2013
Rehabilitate Mott Avenue Station - Rockaway Line   Complete   $6,371,300 $11,111,300 74% May 2008 Sep 2009 Oct 2011 Mar 2012
Rehabilitate Beach 90th Street Station - Rockaway Line   Complete   $7,727,900 $19,302,179 150% May 2008 Jan 2009 Feb 2011 May 2012
Rehabilitate Beach 98th Street Station - Rockaway Line   Complete   $8,442,100 $19,635,245 133% May 2008 Jan 2009 Feb 2011 May 2012
Rehabilitate Beach 105th Street Station- Rockaway Line   Complete   $8,712,900 $18,390,407 111% May 2008 Jan 2009 Feb 2011 May 2012
Rehabilitate East 180th Street Station - White Plains Road Line   Complete   $31,195,500 $43,726,372 40% Jan 2008 Sep 2009 Mar 2011 May 2012
Reconstruct Cortlandt Street Station - Broadway-7th Avenue Line - Design Only   Complete   $80,000,000 $5,576,166 (93%) Jan 2013 Dec 2006 Apr 2008 Apr 2008
Station Accessibility (ADA) - Bleecker-Broadway/Lafayette Street Station Complex   Complete   $8,900,000 $16,367,711 84% Jun 2010 Jul 2008 Nov 2011 Nov 2012
Station Accessibility (ADA) 59th Street - Columbus Circle Station Complex   Complete   $2,652,200 $3,072,056 16% Jul 2005 Dec 2005 Feb 2009 Apr 2011
Station Accessibility (ADA) Kings Highway Station - Brighton Line   Complete   $6,932,700 $9,735,259 40% Dec 2005 Oct 2008 Jun 2010 Dec 2011
Station Accessibility (ADA) Jay Street Station - Fulton Line   Complete   $13,663,000 $13,865,396 1% Aug 2006 Mar 2007 Mar 2011 Mar 2011
Station Accessibility (ADA) 96th Street Station - Broadway-7th Avenue Line   Complete   $25,742,100 $26,680,026 4% Dec 2006 May 2007 Oct 2008 Nov 2010
Station Accessibility (ADA) Jay Street-Lawrence Street Transfer   Complete   $13,460,000 $15,452,480 15% Aug 2006 Mar 2007 Dec 2010 Mar 2011
Station Accessibility (ADA) Mott Avenue - Rockaway Line   Complete   $2,109,800 $10,457,417 396% May 2008 Sep 2009 Oct 2011 Mar 2012
Station Accessibility (ADA) East 180th Street Station - White Plains Road Line   Complete   $7,312,100 $9,335,542 28% Jan 2008 Sep 2009 Mar 2011 May 2012
Passenger Transfer: Bleecker-Broadway/Lafayette Streets   Complete   $31,900,000 $78,582,705 146% Jun 2010 Jul 2008 Nov 2011 Nov 2012
Passenger Transfer: Lawrence Street/Jay Street Stations   Complete   $60,812,000 $56,948,970 (6%) Aug 2006 Mar 2007 Dec 2010 Mar 2011
Station Component Repairs   Complete   $71,000,000 $77,888,832 10% Sep 2008 Jan 2009 May 2012 Oct 2013
Rehabilitate 71st Street Station - West End Line   Complete   $9,863,046 $9,205,433 (7%) Aug 2009 Aug 2009 Feb 2012 Jul 2012
Rehabilitate 79th Street Station - West End Line   Complete   $9,692,282 $9,693,107 0% Aug 2009 Aug 2009 Feb 2012 Jul 2012
Rehabilitate 18 Avenue Station - West End Line   Complete   $9,524,620 $8,483,918 (11%) Aug 2009 Aug 2009 Feb 2012 Jul 2012
Rehabilitate 20 Avenue Station - West End Line   Complete   $9,289,389 $7,857,919 (15%) Aug 2009 Aug 2009 Feb 2012 Jul 2012
Rehabilitate 25 Avenue Station - West End Line   Complete   $10,010,920 $10,933,148 9% Aug 2009 Aug 2009 Mar 2012 Jul 2012
Rehabilitate Bay 50th Street Station - West End Line   Complete   $9,385,817 $8,088,559 (14%) Aug 2009 Aug 2009 Feb 2012 Jul 2012
Rehabilitate Bay Parkway Station - West End Line   Complete   $23,177,881 $20,340,848 (12%) Aug 2009 Aug 2009 Feb 2012 Jul 2012
Station Accessibility (ADA) Bay Parkway Station - West End Line   Complete   $13,357,713 $10,319,758 (23%) Aug 2009 Aug 2009 Feb 2012 Jul 2012
Rehabilitate Fort Hamilton Parkway Station - West End Line   Complete   $26,082,960 $22,316,660 (14%) Aug 2009 Aug 2009 Jan 2012 Nov 2012
Rehabilitate 62nd Street Station - West End Line   Complete   $20,054,536 $17,948,749 (11%) Aug 2009 Aug 2009 Jan 2012 Nov 2012
Rehabilitate 9 Avenue Station - West End Line   Complete   $22,024,929 $19,700,214 (11%) Aug 2009 Aug 2009 Jan 2012 Nov 2012
Station Work 50th Street Station - West End Line   Complete   $9,644,738 $8,590,026 (11%) Aug 2009 Aug 2009 Jan 2012 Nov 2012
Station Work 55th Street Station - West End Line   Complete   $9,805,845 $8,746,453 (11%) Aug 2009 Aug 2009 Jan 2012 Nov 2012
Install Induction Loops for 642 Station Booths   Complete   $20,000,000 $7,156,006 (64%) Aug 2009 Aug 2009 May 2012 Apr 2012
Gap Fillers Union Square Station Phase 3   Complete   $27,150,000 $25,793,406 (5%) Aug 2009 Aug 2009 May 2011 Jul 2011
New York City Transit - Track
Mainline Track Replacement 2009   Complete   $147,815,300 $186,551,727 26% Jan 2009 Jan 2009 Dec 2009 Dec 2009
Track Force Account 2009   Complete   $35,000,000 $35,000,000 0% Jan 2009 Jun 2009 Dec 2009 Dec 2009
30 Mainline Switches In-house 2009   Complete   $45,875,900 $41,627,227 (9%) Jan 2009 Jan 2009 Dec 2009 Dec 2009
New York City Transit - Line Equipment
Tunnel Lighting 42nd Street to 96th Street - Broadway-7th Avenue Line   Complete   $42,129,700 $43,088,679 2% May 2006 Aug 2006 Nov 2009 Dec 2009
Tunnel Lighting Bergen to West 4th Street - 6th Avenue Line   Complete   $21,328,700 $40,551,544 90% Aug 2007 Feb 2008 Aug 2010 Aug 2010
Tunnel Lighting 4th Avenue Portal to Church Avenue - Culver Line   Complete   $20,000,000 $23,814,216 19% Jan 2009 Dec 2008 Nov 2010 Jan 2011
Fan Rehabilitation 30th Street - 6th Avenue Line   Complete   $120,887,000 $70,011,997 (42%) Oct 2005 Dec 2006 Jun 2009 Dec 2009
Fan Wrap-up work - Archer Avenue Line   Complete   $33,031,500 $64,210,746 94% Oct 2005 May 2007 Jun 2011 Dec 2011
Pumps 3 Locations - Prospect Park Line   Complete   $16,794,500 $19,215,187 14% Apr 2006 Jun 2007 Nov 2009 Dec 2009
Vent Plant Rehabilitation - Jackson Avenue - Queens Boulevard Line   Complete   $85,549,221 $69,169,040 (19%) Jun 2009 Jun 2009 Sep 2012 Jul 2012
New York City Transit - Line Structures
Overcoat Bronx Park East to 241st Street - White Plains Road Line   Complete   $21,160,800 $31,609,026 49% Apr 2006 Jun 2008 Jun 2009 Dec 2011
Rehabilitate Culver Viaduct Phase 2   Complete   $113,197,100 $168,657,956 49% Aug 2007 Mar 2009 Sep 2012 Dec 2015
Ocean Parkway Station Viaduct - Brighton Line   Complete   $24,370,400 $32,910,314 35% Jun 2007 May 2006 Dec 2009 May 2011
Overcoat Whitlock Avenue Portal to Pelham Bay Park - Pelham Line   Complete   $21,388,800 $29,123,870 36% Apr 2006 Apr 2007 Apr 2011 Jun 2014
Rockaway Viaduct Phase 2   Complete   $67,949,300 $21,513,123 (68%) May 2008 Oct 2008 Jun 2011 May 2011
Overcoat 103rd Street to Main Street Portal - Flushing Line   Complete   $10,925,200 $27,042,577 148% Apr 2007 Oct 2008 Dec 2010 Dec 2010
Flooding Mitigation: Various Locations   Complete   $90,000,000 $83,679,242 (7%) Mar 2009 Mar 2008 Aug 2010 Mar 2011
Structural Rehabilitation 63rd Street to Bay 50th Street - West End Line   Complete   $41,803,946 $32,725,082 (22%) Aug 2009 Aug 2009 Feb 2012 Jul 2012
Structural Rehabilitation 9th Avenue to 63rd Street - West End Line   Complete   $15,073,273 $13,647,514 (9%) Aug 2009 Aug 2009 Jan 2012 Nov 2012
New York City Transit - Signals And Communications
Signal Control Modifications Phase 3   Complete   $33,001,200 $32,066,865 (3%) Jun 2006 Sep 2006 Oct 2011 Dec 2011
Signal Cable Replacement   Complete   $18,373,800 $51,516,285 180% Nov 2005 Dec 2005 Aug 2007 Jun 2011
Signal Key-By Circuit Modifications Phase 2   Complete   $38,409,600 $28,081,106 (27%) Jun 2007 Dec 2008 Mar 2013 Apr 2014
Communications-Based Train Control Flushing Line Phase 1 Construction $265,583,600 $398,329,006 50% 2007 Jun 2010 Nov 2016 2017
Signal Modernization White Plains Road Line Phase 3: East 180th Street   Complete   $185,334,900 $289,614,256 56% Jun 2006 Nov 2007 Aug 2011 Nov 2011
Interlocking 4th Avenue - Culver Line   Complete   $222,000,000 $114,992,991 (48%) Jun 2009 Mar 2009 Sep 2012 Dec 2012
Interlockings 5th Avenue, Lexington Avenue - Queens Boulevard Line   Complete   $106,233,500 $147,000,698 38% Sep 2008 Jan 2009 May 2012 Nov 2012
Modernize 3 Interlockings - 8th Avenue Line   Complete   $55,000,000 $134,429,362 144% Apr 2006 Oct 2006 Oct 2009 Jun 2010
Communications-Based Train Control Equipment - 64 R160 Cars - Canarsie Line   Complete   $12,000,000 $71,394,158 495% Jul 2007 Oct 2008 Oct 2008 Mar 2012
Data Network Phase 2 IND/BMT-ATM Option   Complete   $134,190,400 $225,170,135 68% Jul 2006 Feb 2006 Mar 2009 Apr 2012
System-wide Application Migration Phase 2   Complete   $49,225,700 $39,565,841 (20%) Sep 2008 Dec 2005 Sep 2009 May 2009
Copper Cable Replacement: Various locations   Complete   $8,810,000 $10,955,878 24% Oct 2008 Feb 2008 Mar 2012 Jun 2012
Antenna Cable Replacement Phase 2   Complete   $31,599,500 $61,919,385 96% Mar 2006 Apr 2006 Jan 2009 Dec 2013
Public Address / Customer Information Screens - Phase 3 Construction $46,900,000 $106,831,135 128% Oct 2008 Sep 2008 Sep 2011 2018
Heating, Ventilation and Air-Conditioning: Station Communication Rooms   Complete   $28,469,401 $27,444,509 (4%) Oct 2009 Oct 2009 Dec 2010 Dec 2011
New York City Transit - Power
Modernize Dyckman Street Substation   Complete   $22,108,000 $41,935,817 90% Mar 2006 Apr 2007 Mar 2009 Aug 2010
Modernize Caton Avenue Substation   Complete   $22,888,500 $23,666,379 3% Jun 2006 Dec 2006 Jan 2010 Nov 2009
Modernize South Railroad Avenue Substation   Complete   $21,743,300 $20,774,965 (4%) Jul 2008 Jul 2008 Aug 2010 Oct 2010
Rehabilitate Underground Substation Hatchways   Complete   $14,658,600 $19,836,325 35% Oct 2008 Dec 2007 Jul 2012 Apr 2014
Modernize Greeley Substation   Complete   $9,275,200 $30,452,535 228% Mar 2009 Dec 2008 Mar 2012 May 2013
Cable Cranberry Tube, Ducts   Complete   $5,000,000 $32,974,609 559% Sep 2005 Oct 2005 Sep 2008 Oct 2014
Control Cables 4 Substation Control Zones   Complete   $59,201,600 $46,902,992 (21%) Dec 2008 Nov 2007 Dec 2010 Aug 2012
Circuit Breaker House East 180th Street   Complete   $6,000,000 $14,250,857 138% Feb 2007 Nov 2007 Feb 2012 Nov 2011
Jay Street Substation, DC Feeders, Circuit Breaker House #579   Complete   $29,900,000 $35,707,775 19% Jul 2009 Jul 2009 Sep 2011 Apr 2013
Rehabilitate 3 IRT Substation Enclosures   Complete   $13,130,599 $11,178,296 (15%) Jul 2009 Jul 2009 Jan 2011 Jun 2011
New York City Transit - Yards
38th Street Yard Portal Viaduct Retaining Wall   Complete   $10,962,700 $22,029,059 101% Jan 2007 Dec 2008 Jul 2011 Dec 2010
Corona Yard Phase 3 Signals, Track Rehabilitation   Complete   $116,345,000 $112,622,383 (3%) Mar 2006 Sep 2006 Jun 2010 Dec 2010
Yard Fencing Priority 1: 8 Locations   Complete   $29,692,193 $24,026,732 (19%) Sep 2009 Sep 2009 Jan 2012 Dec 2011
Yard Fencing Priority 2: 5 Locations   Complete   $28,200,000 $25,702,879 (9%) Jun 2010 Jun 2010 May 2012 May 2012
New York City Transit - Depots
Reconstruct Clara Hale Depot   Complete   $63,211,200 $278,570,045 341% 2010 Apr 2007 Jul 2013 Oct 2014
East New York Depot Repairs   Complete   $82,306,300 $10,961,009 (87%) Jul 2008 Feb 2009 Feb 2012 Mar 2015
Bus Rapid Transit Phase 1   Complete   $21,948,300 $24,292,872 11% May 2008 Dec 2010 May 2016
New York City Transit - Service Vehicles
Purchase 19 Diesel-Electric Locomotives   Complete   $26,469,200 $79,988,272 202% Jan 2007 Dec 2005 Mar 2010 Jul 2014
New York City Transit - Miscellaneous
Fire Alarm/Sprinklers at 5 Locations   Complete   $10,623,300 $36,328,970 242% Jun 2006 Jan 2009 Oct 2010 Jun 2013
Employee Facilities Rehabilitation 59th Street Station - 8th Avenue Line   Complete   $12,575,500 $10,329,106 (18%) Jul 2005 Dec 2005 Feb 2009 Apr 2011
Employee Facilities Rehabilitation Parkchester-East 177th Street Station - Pelham Line   Complete   $6,061,000 $5,107,735 (16%) Jan 2009 Aug 2009 Jan 2012 Dec 2011
Employee Facilities Rehabilitation East 180th Street Station - White Plains Road Line   Complete   $4,633,800 $6,629,223 43% Jan 2008 Sep 2009 Mar 2011 May 2012
Number of Projects for New York City Transit = 114
 
Long Island Rail Road - Stations
Jamaica Fit-Out Phase 2   Complete   $7,827,398 $21,592,261 176% Jul 2007 Apr 2007 Jul 2010 Aug 2010
Long Island Rail Road - Track
Main Line Corridor Improvements -Hicksville North Siding Construction $3,796,061 $50,621,405 1,234% 2015 Jul 2016 Apr 2017 Sep 2019
Main Line Corridor Improvements -Hicksville Station Improvements Construction $4,089,736 $70,570,083 1,626% 2015 Jul 2016 Jan 2020 Aug 2018
Main Line Corridor Improvements -Divide Supervisory Control & Remote Terminal Units (RTUs)   Complete   $8,675,804 $8,288,838 (4%) Oct 2013 Aug 2012 Jan 2017 Oct 2015
Main Line Corridor Improvements -Ellison Avenue Bridge   Complete   $2,230,093 $14,248,460 539% Dec 2014 Feb 2013 Jun 2014 Jun 2016
Main Line Corridor Improvements -Oyster Bay Branch Improvement with Mineola Drainage   Complete   $5,429,766 $214,292 (96%) 2017 Dec 2012 Mar 2013 Mar 2013
Long Island Rail Road - Line Structures
Atlantic Viaduct, Phase I   Complete   $77,500,000 $83,051,797 7% Mar 2008 Dec 2009 Dec 2009
Atlantic Avenue Viaduct, Phase II(a)   Complete   $77,270,000 $73,064,415 (5%) Aug 2009 Aug 2009 Jun 2011 Nov 2010
Long Island Rail Road - Communications And Signals
Fiber Optic Network   Complete   $64,593,628 $69,995,660 8% Apr 2005 Apr 2005 Dec 2009 Apr 2012
Audio Visual Paging System   Complete   $29,032,386 $30,598,558 5% Dec 2005 Dec 2005 Dec 2009 Dec 2011
Jay, Hall & Dunton Microprocessors   Complete   $16,039,885 $39,011,291 143% Sep 2005 Sep 2005 Jun 2007 Nov 2010
Long Island Rail Road - Shops And Yards
Life Cycle Maintenance Shop - Design and Construction   Complete   $35,100,000 $44,583,607 27% Sep 2008 Sep 2009 Mar 2011 Nov 2011
Long Island Rail Road - Power
Replace 3 Substations   Complete   $35,215,521 $35,767,932 2% Sep 2006 Mar 2007 Dec 2009 Sep 2010
Demolish / Construct 6 Substations   Complete   $45,893,731 $57,662,771 26% Mar 2005 Mar 2007 Jan 2010 Jun 2012
Number of Projects for Long Island Rail Road = 14
 
Metro-North Railroad - Stations
Hudson Line Stations Improvements   Complete   $94,100,000 $88,535,487 (6%) Sep 2005 Dec 2006 Apr 2011 Nov 2010
Croton-Harmon and Peekskill Station Improvements   Complete   $5,300,000 $19,030,657 259% Oct 2010 Oct 2010 Oct 2012 Aug 2016
New Haven Line Stations Improvements   Complete   $34,300,000 $21,159,940 (38%) Sep 2008 Jun 2009 Nov 2010 Mar 2011
Cortlandt Parking and Access Improvements   Complete   $29,300,000 $33,063,007 13% Sep 2009 Sep 2009 Dec 2011 Feb 2012
Tarrytown Station Improvement   Complete   $38,061,000 $33,330,990 (12%) Jun 2009 Jun 2009 Apr 2012 May 2012
Metro-North Railroad - Track And Structures
Turnouts: Mainline / High Speed   Complete   $44,600,000 $49,586,829 11% Feb 2008 Feb 2005 Jun 2009 Dec 2010
West of Hudson Improvements Track Program   Complete   $36,700,000 $31,280,897 (15%) Feb 2005 Feb 2005 Jan 2010 Jan 2010
Metro-North Railroad - Communications And Signals
Signal System Replacement   Complete   $28,000,000 $34,981,932 25% Mar 2005 Mar 2009 Dec 2012 Aug 2016
Metro-North Railroad - Power
Harlem and Hudson Lines Power   Complete   $44,200,000 $7,639,872 (83%) Dec 2007 Jul 2009 Oct 2012 Jun 2013
Number of Projects for Metro-North Railroad = 9
 
Bridges and Tunnels - Structures
Deck and structural rehabilitation - Cross Bay Bridge.   Complete   $48,844,604 $63,064,653 29% May 2006 May 2007 May 2008 May 2010
Structural steel repairs at the suspended spans and tower spans of the Throgs Neck Bridge.   Complete   $8,680,329 $35,456,554 308% 2010 Jun 2011 Jul 2013 Dec 2013
Bridges and Tunnels - Roadways & Decks
Elevated and on grade approach deck replacement at Whitestone Bridge.   Complete   $133,079,640 $198,314,140 49% Oct 2008 Oct 2008 Oct 2010 Aug 2012
Lower level deck replacement at Henry Hudson Bridge.   Complete   $50,850,665 $83,444,649 64% Sep 2006 Sep 2006 May 2009 Jun 2010
Replacement of decks at Randall's Island and Ward's Island Viaduct and new ramps at Robert F. Kennedy Bridge.   Complete   $276,368,861 $245,793,908 (11%) Aug 2005 Aug 2005 Jun 2005 Jun 2009
Replacement of concrete deck and rehabilitation of the abutment and retaining walls of the Queens Approach to Throgs Neck Bridge.   Complete   $17,678,918 $69,637,393 294% Jul 2007 Jul 2008 Apr 2008 Apr 2011
Rehabilitate Suspended Decks, Upper Level - Verrazano Narrows Bridge   Complete   $66,258,085 $51,981,996 (22%) Dec 2009 Dec 2008 Dec 2012 Jun 2010
Number of Projects for Bridges and Tunnels = 7
 
Capital Construction - East Side Access
ESA: Grand Central Terminal Concourse Civil & Structural   Complete   $617,721,713 $555,724,483 (10%) Apr 2007 Apr 2008 Oct 2012 Jun 2013
ESA: 50th Street Ventilation Facility   Complete   $122,997,239 $95,576,942 (22%) Jan 2008 Jan 2010 Jul 2012 Mar 2014
ESA: Construction of various infrastructure elements at Harold Interlocking (Part 1)   Complete   $164,704,300 $209,468,375 27% 2007 Jan 2008 May 2010 Feb 2016
ESA: Harold Interlocking Force Account work Construction $175,106,993 $128,038,358 (27%) Jun 2007 Jun 2007 Nov 2010 Dec 2020
ESA: Harold CILs & Communication System Construction $61,683,544 $39,543,815 (36%) Sep 2008 Mar 2009 Nov 2012 Sep 2018
ESA: Queens Bored Infrastructure   Complete   $534,309,074 $736,403,018 38% Sep 2008 Sep 2009 Sep 2012 Apr 2014
ESA: Madison Yard Demolition   Complete   $66,557,332 $42,458,228 (36%) Dec 2008 Dec 2008 Jun 2010 Apr 2011
Capital Construction - Second Avenue Subway
Second Avenue Subway: Contract 2A - 96th Street Station   Complete   $0 $381,201,457 0% May 2008 May 2009 Apr 2012 Nov 2013
Second Avenue Subway: Contract 4B - 72nd Street Station Structure   Complete   $649,264,692 $454,710,180 (30%) Jul 2009 Oct 2010 Oct 2013 Jan 2014
Second Avenue Subway: Contract 5A - 86th Street Station Structure   Complete   $0 $51,270,153 0% Jul 2009 Jul 2009 Sep 2011 Nov 2011
Second Avenue Subway: Contract 6: Systems Construction $0 $315,902,027 0% 2009 Jan 2012 May 2016 Dec 2017
Capital Construction - Flushing Line Extension
Reserve Funds for Work beyond Running Tunnel for the Extension of the #7 Subway Line   Planning  $1,910,000,000 $2,765,710 (100%) 2006 Dec 2013 2018
Construction Management Services for the Extension of #7 Subway Line Construction $60,000,000 $70,743,572 18% 2010 Feb 2007 2013 2018
Structural and Civil Construction for the Extension of #7 Subway Line   Complete   $900,000,000 $1,160,656,915 29% Dec 2007 Dec 2007 Mar 2012 Apr 2012
Construction work at Site L for the Extension of #7 Subway Line   Complete   $65,504,929 $60,421,240 (8%) Jul 2010 Aug 2012 Oct 2012
Construction work at Site J for the Extension of #7 Subway Line   Complete   $130,990,505 $126,290,477 (4%) Oct 2010 Dec 2012 Jan 2014
Construction work at Site K for the Extension of #7 Subway Line   Complete   $92,414,599 $59,862,931 (35%) Aug 2010 Feb 2013 Nov 2012
Number of Projects for Capital Construction = 17