Capital Plan 2005 - 2009 
Bridges & Tunnels  Budget  Schedule 


Description


Photos


Phase

Original
Budget


Current
Original
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Structures
Deck and structural rehabilitation - Cross Bay Bridge.   Complete   $48,844,604 $63,064,653 29% May 2006 May 2007 May 2008 May 2010
Structural steel repairs at the suspended spans and tower spans of the Throgs Neck Bridge.   Complete   $8,680,329 $35,456,554 308% 2010 Jun 2011 Jul 2013 Dec 2013
Roadways & Decks
Elevated and on grade approach deck replacement at Whitestone Bridge.   Complete   $133,079,640 $198,314,140 49% Oct 2008 Oct 2008 Oct 2010 Aug 2012
Lower level deck replacement at Henry Hudson Bridge.   Complete   $50,850,665 $83,444,649 64% Sep 2006 Sep 2006 May 2009 Jun 2010
Replacement of decks at Randall's Island and Ward's Island Viaduct and new ramps at Robert F. Kennedy Bridge.   Complete   $276,368,861 $245,793,908 (11%) Aug 2005 Aug 2005 Jun 2005 Jun 2009
Replacement of concrete deck and rehabilitation of the abutment and retaining walls of the Queens Approach to Throgs Neck Bridge.   Complete   $17,678,918 $69,637,393 294% Jul 2007 Jul 2008 Apr 2008 Apr 2011
Rehabilitate Suspended Decks, Upper Level - Verrazano Narrows Bridge   Complete   $66,258,085 $51,981,996 (22%) Dec 2009 Dec 2008 Dec 2012 Jun 2010
Number of Projects for Bridges and Tunnels = 7