Contract No.: CM-1190
Title: Consultant Design Services for Phase 2 of the Second Avenue Subway Project
Firm: Phase 2 Partnership, a Joint Venture of Parsons Brinckerhoff, Inc. and STV Incorporated
Phone No: (212) 465-5000
Award Date: December 30, 2016
Award Amount: Not-To-Exceed $120,453,095
DBE Goal: 17% DBE
This Contract contains funding provided by the U.S. Department of Transportation through a Grant from the Federal Transit Administration*

Contract No.: CM-1191
Title: Environmental Consultant Services for Phase 2 of the Second Avenue Subway Project
Firm: AKRF, Inc.
Phone No: (212) 696-0670
Award Date: December 19, 2016
Award Amount: Not-To-Exceed $2,342,188
DBE Goal: 17% DBE
This Contract contains funding provided by the U.S. Department of Transportation through a Grant from the Federal Transit Administration*

Contract No.: CH061A
Title: Track A Cut and Cover Structure for the East Side Access Project
Firm: Michels Corporation
Phone No: (212) 230-2700
Award Date: November 22, 2016
Award Amount: $34,074,520
DBE Goal: 17% DBE
This Contract contains funding provided by the U.S. Department of Transportation through a Grant from the Federal Transit Administration

Contract No.: PS860
Title: Consultant Design Services for MTAPD District 9 Facility
Firm: di Domenico + Partners, LLP
Phone No: (212) 337-0400
Award Date: September 16, 2016
Award Amount: $809,815
DBE Goal: 15% MBE, 15% WBE

Contract No.: SAS MP 1
Title: Furnish and Install Equipment for the 72nd, 86th and 96th St. Stations for the Second Avenue Subway Project
Firm: Shazi Construction Company, Inc.
Phone No: (718) 686-8711
Award Date: August 25, 2016
Award Amount: $1,644,000
DBE Goal: 17% DBE
This Contract contains funding provided by the U.S. Department of Transportation through a Grant from the Federal Transit Administration and was awarded through the MTA’s Small Federal Business Program

Contract No.: CM007
Title: Grand Central Terminal Station Caverns and Track for the East Side Access Project
Firm: Tutor Perini Corporation
Phone No: (914) 739-1908
Award Date: April 11, 2016
Award Amount: $663,077,800
DBE Goal: 17% DBE
This Contract contains funding provided by the U.S. Department of Transportation through a Grant from the Federal Transit Administration

Contract No.: VQ033
Title: Mid Day Storage Yard Signal Central Instrument Location and Supervisory Control System for the East Side Access Project
Firm: Ansaldo STS USA, Inc.
Phone No: (412) 688-2400
Award Date: January 15, 2016
Award Amount: $18,498,908
DBE Goal: 0% DBE
This Contract contains funding provided by the U.S. Department of Transportation through a Grant from the Federal Transit Administration

Contract No.: CH057
Title: Harold Structures Part III
Firm: Tutor Perini Corporation
Phone No: (914) 739-1908
Award Date: December 3, 2015
Award Amount: $53,352,586
DBE Goal: 17% DBE
This Contract contains funding provided by the U.S. Department of Transportation through Grants from the Federal Transit Administration and from the Federal Railroad Administration